Question
Working alone, B can complete the work in 20 days. C is
twice as efficient as B and A takes 2 days more than it takes C to complete the work. Working together, in how much time would they be able to complete 7 such works?Solution
Time taken by B to complete the work = 20 days Time taken by C to complete the work =20/2 = 10 days Time taken by A to complete the work alone = 10 + 2 = 12 days Work done by A, B and C together in 1 day. ⇒ (1/20+ 1/10 + 1/12) = (3 + 6 + 5)/60 = 14/60 this means if would take 30/7 days for A, B and C to complete the work together ∴ Time taken A, B and C to complete 7 works = 7 × 30/7 days = 30 days
According to RBI guidelines, what is the maximum loan limit per individual against shares, debentures, and bonds?
The 4Cs approach often mentioned in cluster development refers to:
Head office building is committed to sale; criteria for “held for sale” are met. Will the depreciation still be provided?
UPI stands for ________.
A company faces a lawsuit for patent infringement. Legal advisors state a 55% probability of losing with damages of ₹50 crore, but range could be ₹4...
Calculate sales to earn a profit of Rs. 150,000, if fixed cost = Rs. 3,00,000 and P/V ratio is 20%:
Capital budgeting is done for _________.
Net profit before tax = Rs. 8,00,000. Depreciation = Rs. 1,50,000. Increase in debtors = Rs. 80,000. Increase in creditors = Rs. 60,000. Income tax paid...
What is the limit of UPI transaction for insurance?
For more than three years (unsecured) doubtful advances, provision will be made for