Question
A contractor decided to complete the work in 15 days and
employed 20 men at the beginning and 40 men additionally after 10 days and got the work completed as per schedule. If he had not employed the additional men, how many extra days would he have needed to complete the work?Solution
If he had not employed the additional men, then let work completes in T days. So as by chain rule, Men × time = constant So, 20 × 10 + (20+40) × 5 = 20 × T 200 + 300 = 20T T = 500/20 = 25 days So work delayed for = 25 - 15 = 10 days.
Which initiative is part of the Indian government’s efforts to digitize agriculture?
As per Economic Survey 2024-25, Approximately what percentage of India’s population is supported by the Agriculture and Allied Activities sector?Â
According to the UPAG portal, what is the share of Agriculture & Allied Sectors in India’s Total Gross Value Added (GVA) for 2024-25?
What is the budgetary allocation for the Pradhan Mantri Kisan samman nidhifor the finnancial year 2024-25?
What is the focus of the Pradhan Mantri Annadata Aay Sanrakshan Yojna (PM-AASHA)?
Which state is the largest producer of wheat in 2023-24 (Third Advance Estimate)?
The WINDS system, an instrumental innovation, leverages advanced weather data analytics to provide stakeholders with actionable insights on weather, WIN...
As per the data released by Directorate of Economics and statistics, Ministry released in May 2022 , what is the value of Net Sown Area of India.
What was the budget allocation for agriculture and allied sectors this year (2025-26)?
Share of Agri & Allied sector in Total GVA (2020-21) Â at Current Prices is