Question
 If 15 women or 18 men or 12 boys can do a piece of
work in 18 days of 10 hours each, find how many boys assisted by 5 women and 6 men will finish the same work in 20 days of 6 hours each.Solution
Given, 15 women = 18 men = 12 boys ∴ 1 woman = 6/5 men, 1 boy = 3/2 = 1.5 men Now, 5W + 6M =12 M Total number of men required = 18 X 18/20 X 10/6 = 27 Number of men already present = 12 Hence, 15 men more are required. ∴ No. of boys required = 10
Which countries does the Somali Current flow past in the Western Indian Ocean?
Consider the following statements concerning the Peninsular block of India:
1. The Thar Desert is part of the Peninsular block.
2. Th...
What phenomenon occurs during Equinox days?
How long does it take for light to travel from the Moon to Earth?
‘Palk Strait’ is a narrow channel of sea between-
Which of the following is the highest peak in the world?
Which direction does the Nile River flow?
Which ocean is the smallest by surface area?
In which one of the following islands of India is an active volcano found?
Machkund Hydroelectric Project is a joint venture of which states?