Question
 If 15 women or 18 men or 12 boys can do a piece of
work in 18 days of 10 hours each, find how many boys assisted by 5 women and 6 men will finish the same work in 20 days of 6 hours each.Solution
Given, 15 women = 18 men = 12 boys ∴ 1 woman = 6/5 men, 1 boy = 3/2 = 1.5 men Now, 5W + 6M =12 M Total number of men required = 18 X 18/20 X 10/6 = 27 Number of men already present = 12 Hence, 15 men more are required. ∴ No. of boys required = 10
Electrical fuse is used to interrupt excess of _________.
Which of the following statements best describes the relationship between static friction and the normal force?
Which Nobel Gas is also known as ‘Stranger Gas’?
The S.I. unit of the electric flux is
What type of image is always formed by a convex mirror?
The motion of a freely falling body is an example of ______________ accelerated motion.
Which of the following Instrument is used to measure humidity?
The Atom Bomb dropped in Nagasaki is an uncontrolled nuclear fission made up of:
The instrument which uses sound waves to measure the depth of oceans is –
Mercalli scale is the instrument used for measuring the intensity of ___________.