πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      'A' alone can do some work in 12 days. 'B' is 50% more

      efficient than 'A'. 'A' worked alone for 3 days and left. How much time (in days) does 'B' need to finish the remaining work?
      A 5 days Correct Answer Incorrect Answer
      B 6 days Correct Answer Incorrect Answer
      C 4 days Correct Answer Incorrect Answer
      D 9 days Correct Answer Incorrect Answer
      E 8 days Correct Answer Incorrect Answer

      Solution

      Let the efficiency of 'A' be x units/day.
      So, efficiency of 'B' = 1.5x units/day.
      Total work = 12 Γ— x = 12x units.
      Work done by 'A' in three days = 3 Γ— x = 3x units.
      Remaining work = 12x βˆ’ 3x = 9x units.
      Time taken by 'B' to finish the remaining work = ({9x/1.5x} = 6) days.

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question