ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    'A' alone can do some work in 12 days. 'B' is 50% more

    efficient than 'A'. 'A' worked alone for 3 days and left. How much time (in days) does 'B' need to finish the remaining work?
    A 5 days Correct Answer Incorrect Answer
    B 6 days Correct Answer Incorrect Answer
    C 4 days Correct Answer Incorrect Answer
    D 9 days Correct Answer Incorrect Answer
    E 8 days Correct Answer Incorrect Answer

    Solution

    Let the efficiency of 'A' be x units/day.
    So, efficiency of 'B' = 1.5x units/day.
    Total work = 12 ├Ч x = 12x units.
    Work done by 'A' in three days = 3 ├Ч x = 3x units.
    Remaining work = 12x тИТ 3x = 9x units.
    Time taken by 'B' to finish the remaining work = ({9x/1.5x} = 6) days.

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question