Question
'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 20 days. 'A' started the work alone and worked on it for 2 days, then 'B' alone worked on it for 16 days and 'C' alone completed the remaining work in 18 days. Find the time taken by 'B' alone to complete the whole work.
Solution
Let the total work be 60 units. {LCM of 12 and 20} Combined efficiency of 'A' and 'B' = 60 Γ· 12 = 5 units/day Combined efficiency of 'B' and 'C' = 60 Γ· 20 = 3 units/day Work done by A in 2 days = 2a units
Work done by B in 16 days = 16b units
Work done by C in 18 days = 18c units a + b = 5
b + c = 3 So, a = 5 β b and c = 3 β b 2(5 β b) + 16b + 18(3 β b) = 60
10 β 2b + 16b + 54 β 18b = 60
64 β 4b = 60
4b = 4
b = 1 unit/day Time taken by 'B' alone = 60 Γ· 1 = 60 days
- A alone can complete 60% of a work in 36 days while B takes 30 days more than A to complete it. If B and C together can complete the work in 40 days, then ...
- (y+40) boys can do a piece of work in (z-20) days. (y-5) boys can do the same piece of work in (z+20) days. If (y+30) boys can do the same piece of work in...
- P alone can finish a piece of work βMβ in 8 days while Q takes 4 days to finish it alone. P, Q and R working together can finish the work βNβ which is 7 ti...
- A can complete a work in 10 days and B can complete it in 15 days. In how many days will they complete the work together?
- A civil contractor planned to build an over bridge of 3 km distance in 600 days. For this purpose, he employed 90 workers. After 200 days of work, it was o...
- Number of days taken by βPβ, βQβ and βRβ to do a certain work alone is (x + 4) days, (x - 11) days and (x - 1) days, respectively and number of days taken ...
- A is thrice as efficient as B and can finish a piece of work in 28 days less than B. B can finish this work in how many days?
- The ratio of efficiencies of Ajay and Bijay is 7:8, respectively. Ajay and Bijay together can complete the total work in 24 days. In how many days will Bij...
- P and Q can complete a work in 38 days and 57 days, respectively. P, Q and R together can complete the work in 19 days. If R get a total wage of Rs. 6270 t...
- A can do a piece of work in 28 days, while B can do the same piece of work in 42 days. They begin working together and 6 days before completion of work, A ...