Question
M, N and O can complete a task in βtβ, 100, and βt
+ 20β days respectively. All three started together, but after 15 days, N dropped out. Then, 30 days before the work finished, M also left. The work was finished in 60 days. Find the value of βtβ.Solution
ATQ,
M worked for 30 days, N worked for 15 days and O worked for 60 days So according to question: (30/t) + (15/100) + (60/(t + 20)) = 1 β (30/t) + (60/(t+20)) = 1 β (3/20) β (30t + 600 + 60t)/(tΒ² + 20t) = 17/20 β 17tΒ² + 340t = 600t + 12000 β 17tΒ² β 260t β 12000 = 0 β 17tΒ² β 340t + 80t β 12000 = 0 β 17t(t β 20) + 80(t β 20) = 0 β (17t + 80)(t β 20) = 0 β t = 20 (valid), t = -80/17 (not valid)
- There were 25 workers to complete a job in 10 days. But after 4 days, 10 workers were reassigned. How many more days will be needed now?
If Pawan can do a piece of work in 6 days and Mantu can complete the same work in 2 days, then in how many days will both of them together complete the ...
A and B individually can complete the work in 28 days and 42 days respectively. If the time taken by C alone to complete the work is 1.25 times the time...
Naina and Kalpana working together can do a piece of work in 10 days, whereas Naina alone can do it in 12 days. In how many days can Kalpana do it alone?
Twenty laborers can complete a piece of work in 12 days. If 20 laborers started working and after 3 more days, additional laborers joined to complete th...
Rahul, Rohit, and Raj alone can complete a project in 40, 80, and 120 days respectively. All of them started working together, but after 10 days, Rahul ...
P and Q can complete a work in 38 days and 57 days, respectively. P, Q and R together can complete the work in 19 days. If R get a total wage of Rs. 627...
- Priya completes 30% of a task in 9 days. Her efficiency is 50% greater than Meera's. How many days will it take for both Priya and Meera, working together,...
20 boys can dig a pit in 15 days, while 5 men can dig the same pit in 6 days. In how many days will 10 boys and 1 man together dig the pit?
If a group of 12 boys and 18 girls together can complete a task in 24 days, and a team of 6 girls alone can finish the same task in 96 days, how long wi...