Question
Ritu completes 50% of a project in 25 days, while Sheetal
completes 40% in 32 days. Ritu works for 30 days and then stops. Find the time Sheetal needs to finish the pending work.Solution
ATQ,
Time taken by Ritu to complete whole work = (25 / 0.50) = 50 days
Time taken by Sheetal to complete whole work = (32 / 0.40) = 80 days
Let the total work be 400 units (LCM of 50 and 80)
Efficiency of Ritu = (400 / 50) = 8 units/day
Efficiency of Sheetal = (400 / 80) = 5 units/day
Work completed by Ritu in 30 days = 30 × 8 = 240 units
Remaining work = 400 - 240 = 160 units
Therefore, required time = (160 / 5) = 32 days
Find the average number of platinum tickets sold in theatre B and D, if total number of tickets available in theatre B and D are 250 and 300 respectively.
What is the difference between the number of chocolates purchased by Amit from shop A and B together and number of chocolates purchased by Sumit from sh...
Find the ratio of the number of teachers of school D and ‘b’.
Number of bags sold by A is what percentage more than the number of bags sold by B?
If 30% of the TV sold by shopkeeper S and 25% of the refrigerator sold by shopkeeper S are defective, then find the total number of non-defective items ...
How many students will pass in Computer science if passing marks is more than 46%?
There is another Hall D, number of functions in Hall D in May is 25% more than the Hall A in the same month and number of functions in Hall D in June i...
Find the total number of bags sold by shop B throughout the week.
What is the ratio of the cost of flooring to that of fencing of field S?
The investment made by Indumati in the PF scheme, compared to the LIC scheme, is more by what percentage? (Calculate the approximate value.)