Question
Ritu completes 50% of a project in 25 days, while Sheetal
completes 40% in 32 days. Ritu works for 30 days and then stops. Find the time Sheetal needs to finish the pending work.Solution
ATQ,
Time taken by Ritu to complete whole work = (25 / 0.50) = 50 days
Time taken by Sheetal to complete whole work = (32 / 0.40) = 80 days
Let the total work be 400 units (LCM of 50 and 80)
Efficiency of Ritu = (400 / 50) = 8 units/day
Efficiency of Sheetal = (400 / 80) = 5 units/day
Work completed by Ritu in 30 days = 30 × 8 = 240 units
Remaining work = 400 - 240 = 160 units
Therefore, required time = (160 / 5) = 32 days
Cash-out at any ATM of more than ten hours in a month will attract a flat ₹ _______ penalty?
Where is the headquarters of the Asia-Pacific Economic Cooperation (APEC) located?
विष्व में सर्वाधिक लम्बी तट -रेखा किस खाडी की है ?
Which mobile payment company recently got Prepaid Payment Instrument (PPI) license from RBI
During the Santhal rebellion, who led an army of 1,000 women?
There was a prescribed aim under the National Population Policy, 2000, that a stability will be achieved in population by the year 2045 Now the target y...
A 10 year old skater Rhythm Mamania has clinched the title of climbing Mount Everest in the 11 day expedition. She belongs to which state of India?
The Padmaja Naidu Himalayan Zoological Park in Darjeeling was shortlisted as a finalist for which award in 2024?
Which one of these online marketplaces becomes the first major platform to offer direct mutual funds to consumers?
During which dynasty's rule was the Modhera Sun Temple, a protected monument in Gujarat, constructed?