Question
Ritu completes 50% of a project in 25 days, while Sheetal
completes 40% in 32 days. Ritu works for 30 days and then stops. Find the time Sheetal needs to finish the pending work.Solution
ATQ,
Time taken by Ritu to complete whole work = (25 / 0.50) = 50 days
Time taken by Sheetal to complete whole work = (32 / 0.40) = 80 days
Let the total work be 400 units (LCM of 50 and 80)
Efficiency of Ritu = (400 / 50) = 8 units/day
Efficiency of Sheetal = (400 / 80) = 5 units/day
Work completed by Ritu in 30 days = 30 × 8 = 240 units
Remaining work = 400 - 240 = 160 units
Therefore, required time = (160 / 5) = 32 days
 In a certain code language, ‘BEST’ is coded as ‘4982’ and ‘STEM’ is coded as ‘6489’. What is the code for ‘B’ in that language?
Select the option that is related to the third word in the same way as the second word is related to the first word.
Potato : Â stem : Gram : ?
Select the number from among the given options that can replace the question mark (?) in the following series.
23, 27, 43, 79, 143, ?
Select the option that is related to the third word in the same way as the second word is related to the first word.
Cygnet : Swan :: Colt : ?Â
Given below is a statement followed by possible reasons. Read the statement carefully and decide which one explains the event observation information gi...
In a certain code language, 'MINT' is coded as '9735' and 'NEAR' is coded as '4568'.
What is the code for 'N' in the given code language?Â
Select the number from among the given options that can replace the question mark (?) in the following series?
20, 25, 24, 30, 32, 35, ?
Select the correct mirror image of the given figure when the mirror is placed at MN.
Statements: All computers are laptops. Some laptops are heavy. All heavy is wood.
Conclusion I: All laptops are computers.
Conclusion II: ...
Two statements are given followed by three conclusions numbered I, II and III. Assuming the statements to be true, even if they seem to be at variance w...