Question
Karan can do 60% of a job in 36 days while Meena does 20%
in 18 days. Karan works for 20 days and stops. Calculate how many days Meena will take to complete the rest of the work.Solution
ATQ,
Time taken by Karan to complete whole work = (36 / 0.60) = 60 days
Time taken by Meena to complete whole work = (18 / 0.20) = 90 days
Let the total work be 180 units (LCM of 60 and 90)
Efficiency of Karan = (180 / 60) = 3 units/day
Efficiency of Meena = (180 / 90) = 2 units/day
Work completed by Karan in 20 days = 20 × 3 = 60 units
Remaining work = 180 - 60 = 120 units
Therefore, required time = (120 / 2) = 60 days
According to the Union Budget 2023-24, consider the following statements.
1. The Revised Estimate of the fiscal deficit is 6.4 percent of GDP, ad...
Consider the following statements regarding the National Payments Corporation of India (NPCI):
1. It is an initiative of the Reserve Bank of Indi...
 Calculate Rate on Return on Capital Employed:
According to the revised review of regulatory framework for Housing finance company (HFCs), what is the reduced ceiling on the quantum of public deposit...
Which of the following statements is incorrect about the Indian economy as the Indian Budget 2023-24?Â
Which of the following is a feature of a defined contribution pension plan?
1) Guaranteed payout at retirement
2) Employee bears the inves...
According to the revised SEBI Circular, when are employees now required to place their bids for OFS?
Which is correct step by step process of risk management:
Which of the following is NOT a benefit of career development and management systems for managers?
Which of the following is incorrect when we talk about the PMEGP scheme? Â