Question
Karan can do 60% of a job in 36 days while Meena does 20%
in 18 days. Karan works for 20 days and stops. Calculate how many days Meena will take to complete the rest of the work.Solution
ATQ,
Time taken by Karan to complete whole work = (36 / 0.60) = 60 days
Time taken by Meena to complete whole work = (18 / 0.20) = 90 days
Let the total work be 180 units (LCM of 60 and 90)
Efficiency of Karan = (180 / 60) = 3 units/day
Efficiency of Meena = (180 / 90) = 2 units/day
Work completed by Karan in 20 days = 20 × 3 = 60 units
Remaining work = 180 - 60 = 120 units
Therefore, required time = (120 / 2) = 60 days
The mean proportion of 289 and 144 is:
If all the prime digits of the number 6493858573 are written first (in increasing order) followed by even digits(in increasing order) and then odd digit...
In a locality, all the local electricians follow a cost-plus method to charging fees for their services. The electrician charges for all items used in t...
When the digits, which are odd in the number ‘43289567’ are decreased by 2 and the remaining digits are increased by 1, then what is the product of ...
If the first and second letter of each word are interchanged and words arranged in alphabetical order from left to right then which of the following is ...
How many meaningful English words can be formed from interchanging first and second letters of each word given in the series?
Which Chrome browser feature lets you browse without storing browsing history or saving cookies?
How many steps will be required to get the final output from the following input?
Input: 183 35 553 201 273 249 511 91
Select the option that is related to the third number in the same way as the second number is related to first number and the sixth number is related t...
If K and M interchanged their positions then how many seats are there between M and R?