Question
Karan can do 60% of a job in 36 days while Meena does 20%
in 18 days. Karan works for 20 days and stops. Calculate how many days Meena will take to complete the rest of the work.Solution
ATQ,
Time taken by Karan to complete whole work = (36 / 0.60) = 60 days
Time taken by Meena to complete whole work = (18 / 0.20) = 90 days
Let the total work be 180 units (LCM of 60 and 90)
Efficiency of Karan = (180 / 60) = 3 units/day
Efficiency of Meena = (180 / 90) = 2 units/day
Work completed by Karan in 20 days = 20 × 3 = 60 units
Remaining work = 180 - 60 = 120 units
Therefore, required time = (120 / 2) = 60 days
The participants included hundreds of school children who went their first taste of yoga.
- In the sentence given below four words have been printed in bold which are labeled as (A), (B), (C) and (D) One of these words may be misspelt or inappropr...
This time, the MLAs will rise (A) the issues vigorously (B) so that the government (C) will be forced (D) to reply.
...In each group, one word is correctly spelt. Find the correct word.
- Select the option that corrects the error in the given sentence.
She sings very sweet in the choir every Sunday. - In each sentence below four words have been printed in bold which are numbered (1), (2), (3) and (4) One of these words may be misspelt or inappropriate in...
Choose the word with correct spelling.
Directions: In each question below, four words printed in bold type are given. These are numbered (A), (B), (C) and (D). One these words printed in bol...
- Select the INCORRECTLY spelt word.
Though daily infections had gradually dipped (A)/at the start from the year, the relief was short-lived (B)/as the Delta variant drive (C)/an exponent...