Question
βEβ takes 30 days to complete a job. If βFβ is
50% more efficient than βEβ, how many days will they take together to complete 75% of the work?Solution
Let the work be 100x units.
Efficiency of βEβ = 100x Γ· 30 = β10x/3β units/day
Efficiency of βFβ = (10x/3) Γ 1.5 = β5xβ units/day
75% of the work = 100x Γ 0.75 = 75x units
Required time = 75x Γ· ((10x/3) + 5x) = 75x Γ· ((10x + 15x)/3) = 75x Γ· (25x/3) = 9 days
Which algorithm is commonly used for collaborative filtering in recommendation systems?
Which network topology uses a central node to connect all other nodes?
What is the main advantage of Hadoop's HDFS (Hadoop Distributed File System)?
What is the main purpose of a parser in a compiler?
Which of the following is NOT a potential concurrency control issue?
Which of the following clause return specific rows?
Suppose we have a printer shared between various machines in a network, and any machine or computer in a network can send a print request to the printe...
Which is not in relation to the database.
the star schema is the simplest style of data mart schema and is the approach most widely used to develop data warehouses and dimensional data marts.
Major type of computer chip