Question
A and B can complete a task together in 10 days, while B
alone takes 20 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 15 days. Determine the percentage of the total work completed by A.Solution
Let total amount of work be 20 units
Efficiency of (A + B) = 20/10 = 2 units/day
Efficiency of ‘B’ = 20/20 = 1 unit/day
Amount of work done by ‘B’ = 15 × 1 = 15 units
Percentage of work done by ‘A’ = {(20 – 15)/20} × 100 = 25%
Indian National Centre for Ocean Information Services has launched which app for seafarers?
Which of the following districts of uttarakhand has maximum forest area in percentage as per forest report 2021?
What was the revised economic growth forecast for India in FY2024-25 as per the latest RBI report?
In August 2024, which country witnessed Paetongtarn Shinawatra becoming its youngest Prime Minister?
In which year was the poetry collection 'Jitne Log Utne Prem' by Leeladhar Jagudi, for which he received the Vyas Samman in 2018, published?
The Hundred Years' War was fought between which two countries?
Which organization recently completed six consecutive developmental trials of the High-Speed Expendable Aerial Target (HEAT) 'ABHYAS'?
What is the primary threat to Gangetic river dolphins mentioned in the Freedom on the Net 2023 publication?Â
Mobile application app 'Sarpanch Samvad' was unveiled in which state?
In which year did Madan Mohan Malviya establish "Bharata Dharma Mahamandal" with the aim of propagating Sanatan Dharma and Hindu culture, and also serv...