    Question

    'Y' is 36% less efficient compared to 'X'. If 'X'

    requires 86.4 days to finish a task, determine how many days 'Y' will take to complete the same task.
    A 120 days Correct Answer Incorrect Answer
    B 100 days Correct Answer Incorrect Answer
    C 110 days Correct Answer Incorrect Answer
    D 135 days Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let the efficiency of 'X' be '100e' units/days. Efficiency of 'Y' = 0.64 X 100e = '64e' units/days Ratio of efficiency of 'Y' and 'X', respectively = 64e:100e = 16:25 So, ratio of time taken by 'Y' and 'X', respectively = 25:16 Therefore, required time = (86.4/16) × 25 = 135 days 