πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    ⚑ Month End Offer - Flat 52% Off On All Courses! Enroll Now ⚑
    00:00:00 AM Left

    Question

    'Pawan' can complete a task alone

    in 63 days. However, when working together with 'Bhanu,' they finish the same task in 42 days. How many days would it take for 'Bhanu' to complete the task alone?
    A 126 days Correct Answer Incorrect Answer
    B 120 days Correct Answer Incorrect Answer
    C 135 days Correct Answer Incorrect Answer
    D 140 days Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let the total work be 126 units (LCM of 63 and 42) Efficiency of 'Pawan' = (126/63) = 2 units/day Combined efficiency of 'Pawan' and 'Bhanu' = (126/42) = 3 units/day So, efficiency of 'Bhanu' = 3 - 2 = 1 unit/day Therefore, required time = (126/1) = 126 days

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question