ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!

  • google app store apple app store
  • тЬЦ

      Question

      4 girls working together for 1

      day complete the same amount of work as 6 men working together for 1 day. The efficiency of 1 man is 50% of the efficiency of 1 girl. Additionally, 1 boy, 1 girl, and 1 man together can finish the project in 5 days. How many days will it take for 1 boy to complete the project alone?
      A 22 days Correct Answer Incorrect Answer
      B 18 days Correct Answer Incorrect Answer
      C 12 days Correct Answer Incorrect Answer
      D 10 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ, Since, work done by 4 boy together in 1 day is equal to that done by 6 girls together in 1 day. 4x = 6y 2x = 3y --------(1) Since the ratio of efficiency of one men is 50% of that of one girl. 1y = 2b --------(2) From equations (1) and (2): 2x = 3y = 6b The ratio of time taken by 1 boy, 1 girl and 1 men alone to complete work: 2: 3: 6 Let the time taken by 1 boy, 1 girl and 1 men alone to complete the work be тАШ2pтАЩ, тАШ3pтАЩ and тАШ6pтАЩ days respectively. So, (1/2p) + (1/3p) + (1/6p) = 1/5 p = 5 Time taken by 1 boy alone to complete the work = 2 ├Ч 5 = 10 days

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question