📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      Person 'A' can finish a task in 16 days by working

      alone. Person 'B', who is twice as efficient as 'A', works on the task alone for 3 days. After that, Person 'A' joins 'B'. How much time will it take to complete the task?
      A 13/2 days Correct Answer Incorrect Answer
      B 6 days Correct Answer Incorrect Answer
      C 19/3 days Correct Answer Incorrect Answer
      D 22/3 days Correct Answer Incorrect Answer

      Solution

      Let the total work be 16 units. So, efficiency of 'A' = (16/16) = 1 unit/day So, efficiency of 'B' = 1 X 2 = 2 units/day Work done by 'B' alone in 3 days = 2 X 3 = 6 units Time taken by 'A' and 'B' to complete the remaining work alone = {(16 - 6)/(2 + 1)} = (10/3) days So, total time taken to complete the work = 3 + (10/3) = (19/3) days

      Practice Next

      Relevant for Exams:

      ask-question