Question

A contractor was tasked with constructing a bridge within 45 days. To complete the project, he initially hired 75 workers. However, after 40 days, he discovered that only 75% of the work had been completed. How many additional workers must he hire to ensure the remaining work is finished on schedule?

A 100
B 125
C 150
D 200
E None of these
Practice Next

Hey! Ask a query