Question
A contractor was tasked with constructing a bridge within 45 days. To complete the project, he initially hired 75 workers. However, after 40 days, he discovered that only 75% of the work had been completed. How many additional workers must he hire to ensure the remaining work is finished on schedule?
More Quant Miscellaneous Questions
- I). p2 + 16p + 55 = 0 II). q2 + 9q + 20 = 0
- Question 2
- A person spends 40% of his income on rent, 30% on food, and 20% on education. If he saves ₹2000, what is his total income?
- What is the third proportional to the numbers 12 and 36?
- 6, 8, 15, 44, ?, 1134.
- P, Q, and R are racing on a circular track with a length of 'd' meters. During the race, P finishes 800 meters ahead of Q and 1200 meters ahead of R. Likew...
- P can do a piece of work in 20 days, Q can complete double the work in 40 days and R can do the work in 30 days. If all of them together earn Rs. 2400, the...
- A man is running at a speed of 20 m/s in the same direction as a train. The train passes the man completely in 9 seconds. If the train's speed is 144 km/h,...
- Rakesh can complete a work in 'X + 12' days. While Shikha can complete the same work in 'X + 27' days. If they can complete the work together in 'X' days, ...
- An investor deposits ₹50,000 in a bank that offers a simple interest rate of 8% per annum. How much interest will the investor earn after 3 years, and what...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)