Question
A contractor was tasked with constructing a bridge within 45 days. To complete the project, he initially hired 75 workers. However, after 40 days, he discovered that only 75% of the work had been completed. How many additional workers must he hire to ensure the remaining work is finished on schedule?
More Quant Miscellaneous Questions
- A tank is filled with 3 inlet pipes and 2 outlet pipes. Inlet pipes A, B, and C can fill the tank in 6 hours, 8 hours, and 12 hours, respectively. Outlets ...
- Find the simplified value of the expression: 32 + 12 x 108 ÷ 12 + 4 + 32 ÷ 16 x 3
- If z=2+3i, then arg(z)=θ lies in which quadrant?
- A fruit seller sold 3/5 of his fruits in the first half and 1/2 of the remaining fruits in the second half. If he had 400 fruits at the beginning of the da...
- Find the number of triangles in the given figure.
- The value of tan 225° is same as the value of:
- A rectangular garden has a width of 18 meters and a perimeter of 96 meters. If the garden is to be fenced at a cost of Rs. 12 per meter, what will be the t...
- Rakesh can complete a work in 'X + 12' days. While Shikha can complete the same work in 'X + 27' days. If they can complete the work together in 'X' days, ...
- If a hyperbola passes through the point (4, 0) and has foci at (±5, 0), and the length of its conjugate axis is 6, then the eccentricity is:
- Words given on the left side of (::) are related with each other by some Logic/Rule/Relation. Select the missing word/word pair on the right side of (::) f...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)