Question
A and B can each finish a task in 32 days and 36 days
respectively. They begin the task together, but after 12 days, A leaves. How long will it take for B to complete the remaining work alone?Solution
Let total amount of work = 288 units (LCM of 32 and 36) Amount of work done by A in one day = 288/32 = 9 units Amount of work done by B in one day = 288/36 = 8 units Amount of work done by A and B together in 12 days = 12 × 17 = 204 units Remaining work = 288 – 204 = 84 units Desired time = 84/8 = 10.5 days Hence, option c.
The Internal Ombudsman has been designated to the Credit Information Companies with effect from ________.
Recently scientists of which institute of India have discovered a new star?
Consider the following in regards to the Kotak School of Sustainability :
1) It is India's first fully integrated institution dedicated to sustai...
Which census data forms a key reference point in Ravi K Mishra’s book on demography and delimitation?
_____________ started her sixth ICC Women's World Cup Campaign becoming the first woman to do so.
How much of the Brics + export share was contributed by China in 2023?
Consider the following statements about Pompe disease:Â
1.   Recently, India’s first patient of Pompe disease was cured.Â
2.   ...
Which institute recently signed an MoU with Loopworm, a startup specializing in insect biosciences and bio-manufacturing, to assess the potential of ins...
An autobiography “Resolved: Uniting Nations in a Divided World” is written by?
Which prominent Indian musicians, who are part of the fusion band Shakti, won the Grammy Award in the Best Global Music Album category for their latest ...