Question
'A' and 'B' alone can complete a work in 10 days and 15
days, respectively. If they worked together and total wage received by them to complete the work is Rs. 600, then find the wage received by 'A'.Solution
Let total work = 30 units {LCM of 10 and 15} Efficiency of 'A' = 3 units per day Efficiency of 'B' = 2 units per day Since, they completed the whole work together therefore ratio of wage received by them will be same as the ratio of their efficiencies. So, Required wage received by 'A' = {3/(3 + 2)} X 600 = Rs. 360
‘p’ is how much percent more than that of ‘t’?
The price of each green pen sold by B, C and D is Rs.5, Rs.10 and Rs.12 respectively. Find the total price of all the green pens sold by these three shops.
The Total number of bank aspirants in Chandigarh is what per cent of the total number of bank aspirants in Lucknow?
The number of participants in painting competition is approximately what per cent of the number of participants in recitation?
If the average number of unsold items by company 'B' and 'D', together, who were presented in a competition is 'a', then find the value of 90% of 'a'.
Total number of Umbrella sold in cities C and D together is approximately what percent of the total number of Raincoat sold in cities A and F together?
In match-2, Australia batted first, and the runs scored by Australian batsmen, including the all-rounder, were 85% of the team’s total score. England ...
Number of females in Pune are approximately what per cent of the number of males in Kolkata?
Workers C and D work together for 10 days. Calculate how many units they will complete in this period.
Find the difference between the total comic books sold to total fiction books sold from all the shops together.