Question
Working alone, βXβ and
βYβ can complete a work in 16 days and 10 days, respectively. They started working together but after 4 days, βYβ was replaced by βZβ and the work got finished in the next 4 days. Find the time taken by βZβ alone to finish the whole work.Solution
Let the total work be 80 units (LCM of 16 and 10).
Combined efficiency of X and Y = 5+8=13 units/day. Work done by X and Y together in 4 days = 13Γ4=52 units. Remaining work = 80β52=28 units.
Efficiency of Z = 7β5=2 units/day.
Which component accounted for the largest share of Indiaβs external debt as of March 2025?
Which bank has partnered with the Reserve Bank Innovation Hub to introduce a new customer-friendly service for digital submission of Form 15G/15H to avo...
Dokriani Glacier is located:Β
Which place is said to be Manchester of South India?
Archaeologists have unearthed 3,000-year-old priestly tomb in which country?
What is the name of the week-long program launched by PM Modi on September 30, 2023, to enhance governance at the block level?
Nvidia Corp witnessed a significant surge in its market value after its forecast highlighted the potential of AI spending. By how much did the company's...
Which of the following companies won the 'Road Freight Service Provider' award in the LEAPS 2024 Awards?
Which Indian Naval Ships visited Manila, Philippines as part of their South China Sea operational deployment?
Consider the following statements:
1.Β In the revenue administration of Delhi Sultanate, the in-charge of revenue collection was known as βAmi...