Question
'A' can do 50% of work in 10 days, whereas 'B' can do
25% of the same work in 8 days. 'A' and 'B' started the work, but 'B' left the work 'n' days before completion of work. If the whole work is completed in 15 days, then find the value of [0.8n + (n²/10) ].Solution
ATQ, Time taken by 'A' to complete the entire work = (10/50)×100 = 20 days Time taken by 'B' to complete the entire work = (8/25 )×100 = 32 days Let the total work be 160 units (LCM of 20 and 32). Efficiency of 'A' = 160/20 = 8 units/day Efficiency of 'B' =160/32 = 5 units/day ATQ, (8×15)+{5×(15−n)} = 160 120+(75−5n) = 160 195−5n = 160 5n = 35 n = 7 Therefore, required value =
Which is a commonly used biofertilizer in organic farming?
Which practice helps conserve moisture and control weeds in organic farming?
What does GMP stand for under FSSAI’s hygiene regulations?
What is the full form of SPS in WTO agreements related to agri trade?
APEDA has developed an e-governance platform to assist exporters in registration and related services. What is this platform called?
Under the FSS Regulations 2011, which body is primarily responsible for drafting standards and enforcing food safety across the food chain?
Which Indian organization helps exporters meet international food trade requirements and offers infrastructure support?
The concept of “Minimum Export Price” (MEP) is primarily used to:
The Central Institute for Women in Agriculture (ICAR-CIWA), functioning under Indian Council of Agricultural Research is mandated to undertake research ...
Which of the following is a major traceability system implemented by APEDA for grapes?