Question
βAβ can complete a work in 12 days and is 33.33%
more efficient than βBβ. βAβ and βBβ start the work together, but βAβ leaves after 6 days. The remaining work is completed by βBβ alone in βxβ days. Find the value of βxβ.Solution
Given: A completes the work in 12 days. A is 33.33% more efficient than B, meaning B's rate is 1/16 (since A's rate is 1/12). A and B's combined rate Work done together in 6 days
Remaining Work =Β Β
Work Done by B Alone Bβs rate = 1/16. Time taken by B to finish the remaining work:
In the question given below, a passage is followed by three statements which may or may not be inferred from the passage. Select the correct combinati...
In the question given below, a passage is given followed by three statements which may or may not be inferred from the passage. Select the correct combi...
Statement-
India and Israel elevated their ties to a strategic partnership as India identified Israel as a major development and technological pa...
In the question given below, a passage is given followed by three statements which may or may not be inferred from the passage. Select the correct com...
Consider the following passage, followed by three statements. Determine the correct combination of statements that cannot be inferred from the passage:...
Read the passage below and select the option that best sums up its central idea:
βA man once approached a wise teacher and asked, βHow ca...
In the question given below, a passage is given followed by three statements which may or may not be inferred from the passage. Select the correct com...
There are some criteria which will be considered during appraisal of employee-Statement by manager of a company. Punctuality and sincerity are one of th...
In the question given below, a passage is given followed by three statements which may or may not be inferred from the passage. Select the correct com...
In the question given below, a passage is given followed by four statements which may or may not be inferred from the passage. Select the correct comb...