Question
Before 'A' joined the team, 'S' and 'V' were alternating
days to complete a project. In the final four days, 'A', 'S', and 'V' all worked together to finish the job. 'V' is 50% more efficient than 'S' and 20% more efficient than 'A'. If 'A' can complete the work by himself in 24 days and 'S' and 'V' worked for an equal number of days, calculate the total number of days it took to complete the work.Solution
ATQ, Time taken by 'V' alone to do the work = 24/1.2 = 20 days Time taken by 'S' alone to do the work = 1.5 × 20 = 30 days Let, total work be LCM of 20, 30, and 24 = 120 units Units of work done by 'A', 'V', and 'S' in a day are 5 units, 6 units, and 4 units, respectively. So, units of work done in last 4 days = 15 × 4 = 60 units Remaining 60 units of work done in (60/10) × 2 = 12 days So total number of days = 12 + 4 = 16 days
Which of the following was not a city in Ancient Harappan Civilization?
The substance made from only carbon is
The process by which two immiscible liquids, get mixed while one disperses as small droplets within the other is known as __________
Find the equations of the bisectors of the angle between the straight line 3x + 4y +2 = 0 and 5x – 12y - 6 = 0.Â
With which neighbouring country did India sign the Farakka Treaty in 1996 for sharing of the Ganga Waters and on augmenting its flows?
Which of the following is the SI unit of energy?
Through what financial mechanism did Bank of India (BoI) recently secure ₹4,500 crore by issuing approximately 44.91 crore equity shares at an issue p...
What was the codename of the nationwide Defence Mock Drill Civil operation India conducted on May 07, 2025, across 244 districts of the nation?
The major component of granite is:
In which river has the National Waterways-2 (NW-2) been developed in India?