Question
Rohan can finish a task alone in 24 days. Shreya can do
50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% of the task in 9 days. Find the time taken by Rohan and Tanya to finish the task together.Solution
ATQ, Time taken by Shreya to do the entire task = 12 ÷ 0.5 = 24 days Time taken by Shreya and Tanya to do the entire task together = 9 ÷ 0.6 = 15 days Let the total work be 120 units {LCM (24, 24, and 15)} So, the combined efficiency of Shreya and Tanya = 120 ÷ 15 = 8 units/day Efficiency of Shreya = 120 ÷ 24 = 5 units/day Efficiency of Tanya = 8 - 5 = 3 units/day Efficiency of Rohan = 120 ÷ 24 = 5 units/day So, required time taken = 120 ÷ (5 + 3) = 120 ÷ 8 = 15 days
Who can be the participants in the Call Money Market
1. Scheduled Commercial Banks (excl Local Area Banks)
2. Small Finan...
In India, Treasury bills (T-bills) are auctioned by _____
FIMMDA is a voluntary market body for bond and money markets, with members representing all major institutional segments of the market. What does FIM...
The maximum tenor of Commercial Paper (CP) in India is:
The debt instruments that help to raise money in local currency from foreign investors is called______
Commercial Papers (CP) is a money market instrument used to raise funds for at least ____?