Question
Rohan can finish a task alone in 24 days. Shreya can do
50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% of the task in 9 days. Find the time taken by Rohan and Tanya to finish the task together.Solution
ATQ, Time taken by Shreya to do the entire task = 12 ÷ 0.5 = 24 days Time taken by Shreya and Tanya to do the entire task together = 9 ÷ 0.6 = 15 days Let the total work be 120 units {LCM (24, 24, and 15)} So, the combined efficiency of Shreya and Tanya = 120 ÷ 15 = 8 units/day Efficiency of Shreya = 120 ÷ 24 = 5 units/day Efficiency of Tanya = 8 - 5 = 3 units/day Efficiency of Rohan = 120 ÷ 24 = 5 units/day So, required time taken = 120 ÷ (5 + 3) = 120 ÷ 8 = 15 days
In India, Micro Finance Institutions primarily target which segment of the population?
In which sport does Ayhika Mukherjee excel, as her performance aids India in securing another victory in World Team Championships 2024?
As of October 2020, who among the following is the youngest Nobel Laureate?
The President of which of the following countries was invited as the Chief Guest for the Republic Day parade on 26 January 2020?
In which of the following years did India NOT win an Olympic gold medal in hockey?

Which of the following is a water-borne disease?
On which of the following days, the National Panchayati Raj Day is celebrated?
Life is like a box of chocolate. You never know what you’re going to get.
What is the first step of the process of staffing in an organisation?