    Rohan can finish a task alone in 24 days. Shreya can do

    50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% of the task in 9 days. Find the time taken by Rohan and Tanya to finish the task together.
    A 15 Correct Answer Incorrect Answer
    B 20 Correct Answer Incorrect Answer
    C 18 Correct Answer Incorrect Answer
    D 35 Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    ATQ, Time taken by Shreya to do the entire task = 12 ├╖ 0.5 = 24 days Time taken by Shreya and Tanya to do the entire task together = 9 ├╖ 0.6 = 15 days Let the total work be 120 units {LCM (24, 24, and 15)} So, the combined efficiency of Shreya and Tanya = 120 ├╖ 15 = 8 units/day Efficiency of Shreya = 120 ├╖ 24 = 5 units/day Efficiency of Tanya = 8 - 5 = 3 units/day Efficiency of Rohan = 120 ├╖ 24 = 5 units/day So, required time taken = 120 ├╖ (5 + 3) = 120 ├╖ 8 = 15 days

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question