Armaan and Bhanu working together can finish a certain
task in 90 days, and Bhanu collaborating with Chintu can complete the same task in 70 days. If Armaan's efficiency is 40% less than Chintu, determine the time Armaan alone needs to complete 80% of the work.Solution
ATQ, Let the total work be 630 units. (LCM of 90 and 70) Amount of work done by Armaan and Bhanu together in one day = 630/90 = 7 units Amount of work done by Bhanu and Chintu together in one day = 630/70 = 9 units Difference between the efficiencies of Armaan and Chintu = 9 – 7 = 2 units Amount of work done by Chintu alone in one day = 2/0.40 = 5 units Amount of work done by Armaan alone in one day = 0.6 × 5 = 3 units Time taken by Armaan alone to complete 80% work = 0.8 × 630/3 = 168 days
POST stands for ...........
Select the option that is related to the fifth number in the same way as the second number is related to first number and the third number is related to...
Four numbers have been given, out of which three are alike in some manner and one is different. Select the number that is different.
. In the following question, find which one word cannot be made from the letters of the given word “CORRESPONDENCE”
- How many vowels are to the right of 'P'?
All the words arranged as per the dictionary order then which of the following words is third from the right end?
Arrange the words in the alphabetical order and pick the one that come in the end.
Which of the following chips is powered by a battery?
Which box contains maximum candies?
I. Box A has candies more than Box C and Box E but not more than Box B and Box D.
II. The sum of candi...
Select the option that is related to the third term in the same way as the second term is related to first term.
SURPRISE: IRHVHFIK:: HESITATE: ?