ATQ, Let the total work be 630 units. (LCM of 90 and 70) Amount of work done by Armaan and Bhanu together in one day = 630/90 = 7 units Amount of work done by Bhanu and Chintu together in one day = 630/70 = 9 units Difference between the efficiencies of Armaan and Chintu = 9 – 7 = 2 units Amount of work done by Chintu alone in one day = 2/0.40 = 5 units Amount of work done by Armaan alone in one day = 0.6 × 5 = 3 units Time taken by Armaan alone to complete 80% work = 0.8 × 630/3 = 168 days