Question
Armaan and Bhanu working together can finish a certain task in 90 days, and Bhanu collaborating with Chintu can complete the same task in 70 days. If Armaan's efficiency is 40% less than Chintu, determine the time Armaan alone needs to complete 80% of the work.
More Time and work Questions
- A cheetah can catch a deer running with a speed of 108 km/h and is 66 meters ahead of it, in 12 seconds. Find the time taken by the cheetah to catch a zebr...
- Riya completes 40% of a task in 24 days, while Siya finishes 30% of the same task in 27 days. Riya begins the task alone and stops after 30 days. How long ...
- A can finish a piece of work in 10 days and B can finish the same work in 15 days. If they work together, in how many days will the work be completed?
- A and B together, B and C together and A and C together can complete a piece of work in 44 days, 33 days and 36 days respectively. Find the ratio of the ef...
- A worker finishes 40% of a job in 6 days. At the same rate, how many more days are needed to finish the remaining work?
- ‘A’ and ‘B’ can do a piece of work in 20 days and 30 days, respectively. If they started the work together and worked on it for 7 days, then find the time ...
- Efficiency of a man is 25% more than that of a woman. (2n + 4) men working 8 hours a day can complete a task in 18 days, whereas (3n - 2) women working 6 h...
- Ravi and Rekha, alone can complete a work in 25 days and 50 days, respectively. They started the work together and left after 10 days such that the remaini...
- A can complete a work in 15 days. B takes 5 days less than A to complete the same work. In how many days can both of them together complete 60% of the work...
- A and B together can complete a work in 10 days. B alone can complete the same work in 25 days. In how many days can A alone complete the work?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt