Question
‘A’ can do 30% of the work in 12 days. ‘B’ can
do the whole work in 50 days. Find the time taken by them together to do 75% of the work.Solution
Time taken by ‘A’ to complete the whole work. = 12/0.30 = 40 days Time taken by ‘B’ to complete the whole work. = 50 days Let total work = 200 units (LCM of 50and 40) Efficiency of ‘A’ = 200/40 = 5 units/day Efficiency of ‘B’ = 200/50 = 4 units/day required time taken = (.75×200)/ (5+4) =150/9=16.66days
Palladium on barium sulphate (Pd/BaSO₄) is also known as:
“Magnus Carlsen” is associated with which of the following games?
In 1932, who founded the 'All India Harijan Sangh', also known as 'Harijan Sevak Sangh'?
On whose advice did Gandhiji spend a year travelling around British India to know the people of India?
Consider the following statement about 2023 Gender Social Norms Index:
1. This Index is developed by the UNDP
2. This index covered 60 per...
When was the first ‘Minning Policy’ in Uttarakhand State declared?
India accounts for 45.8 million of the world’s missing females according to the State of World Population 2020 report of:
What is the traditional culinary delight from Odisha’s Mayurbhanj district that recently received a Geographical Indication (GI) tag?
In November 2025, a High-Level Committee chaired by ______ submitted its report on “Conflict of Interest, Disclosures and related matters in respect o...
Whose reign saw the largest extension of Delhi Sultanate?