Question
‘A’ can do 30% of the work in 12 days. ‘B’ can
do the whole work in 50 days. Find the time taken by them together to do 75% of the work.Solution
Time taken by ‘A’ to complete the whole work. = 12/0.30 = 40 days Time taken by ‘B’ to complete the whole work. = 50 days Let total work = 200 units (LCM of 50and 40) Efficiency of ‘A’ = 200/40 = 5 units/day Efficiency of ‘B’ = 200/50 = 4 units/day required time taken = (.75×200)/ (5+4) =150/9=16.66days
Where is the World’s longest suspension footbridge named ‘Sky Bridge 721’ opened for the tourists?
What is the Foreign Contribution Registration Act (FCRA)?
Which missile was tested from INS Arighaat as part of India’s nuclear triad?
In which year did the East India Company acquire the Diwani of Bengal?
 In which state the annual festival of ‘Kadalekai Parishe’, also known as the groundnut festival is being held?
A French architect, Le Corbusier designed which city?
In July 2023, which country successfully launched the 'Methane Liquid Oxygen Fuel Space Rocket'?
Indian Oil Corporation Ltd (IOC) will start manufacturing fuel used in Formula One (F1) racing in three months. What is the name of the petrol unveiled ...
Who chairs the Governing Council of the Skill India Mission?
Eastern Yamuna Canal was constructed in?