‘A’ can do 30% of the work in 12 days. ‘B’ can
do the whole work in 50 days. Find the time taken by them together to do 75% of the work.Solution
Time taken by ‘A’ to complete the whole work. = 12/0.30 = 40 days Time taken by ‘B’ to complete the whole work. = 50 days Let total work = 200 units (LCM of 50and 40) Efficiency of ‘A’ = 200/40 = 5 units/day Efficiency of ‘B’ = 200/50 = 4 units/day required time taken = (.75×200)/ (5+4) =150/9=16.66days
Who sits immediate left of ZAHIR?
Who likes Blue?
Which of the following statement is/are true?
I) T sits second to the right of W
II) Only one person sits between V and Y when counte...
Five people are standing in a ticket booking line. S, U and V are standing together, V is between S and U. S is immediately behind T and W is immediatel...
Six persons D, E, F, G, H and I sit in a linear row and face in the north direction. G sits at an extreme end of the row. Only two persons sit between G...
Six people- T, U, V, W, X and Y are sit along a linear row and face in the north direction. U sits third to the left of W. Neither U nor W sits along th...
Who among the following sits fourth to the right of F?
Who among the following does like fruits Kiwi?
How is U related to M?
Who sits diagonally opposite to T?