📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store

    • Question

      ‘A’ can do 30% of the work in 12 days. ‘B’ can

      do the whole work in 50 days. Find the time taken by them together to do 75% of the work.
      A 20days Correct Answer Incorrect Answer
      B 18days Correct Answer Incorrect Answer
      C 16.6days Correct Answer Incorrect Answer
      D 15days Correct Answer Incorrect Answer

      Solution

      Time taken by ‘A’ to complete the whole work. = 12/0.30 = 40 days Time taken by ‘B’ to complete the whole work. = 50 days Let total work = 200 units (LCM of 50and 40) Efficiency of ‘A’ = 200/40 = 5 units/day Efficiency of ‘B’ = 200/50 = 4 units/day required time taken = (.75×200)/ (5+4) =150/9=16.66days

      Practice Next
      ask-question