πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A can complete a task 40% more efficiently in 25 days,

      whereas B, with a 25% efficiency boost, can finish the same task in 21 days. They collaborated at their original efficiencies for 9 days. Now, how we can determine the time it will take for A to complete the remaining work, reverting to his original efficiency level when working alone.
      A 14 days Correct Answer Incorrect Answer
      B 21 days Correct Answer Incorrect Answer
      C 25 days Correct Answer Incorrect Answer
      D 13 days Correct Answer Incorrect Answer
      E none of these Correct Answer Incorrect Answer

      Solution

      ATQ, Let total amount of work be 525 units Amount of work done by β€˜A’ in one day (with increased efficiency) = 525/25 = 21units Original efficiency of β€˜A’ = 21/1.40 = 15 units per day Amount of work done by β€˜B’ in one day (with increased efficiency) = 525/21 = 25units Original efficiency of β€˜B’ = 25/1.25 = 20 units per day Amount of work completed by β€˜A’ and β€˜B’ together in 9 days = 35 Γ— 9 = 315 units Remaining work = 525 – 315 = 210 units Desired time = 210/15 = 14 day

      Practice Next
      ask-question