Question
A, B and C can complete a work in 10 days, 20 days and
30 days respectively. A and C started the work together and they both work for 6 days. If the remaining work is completed by B and D in 3 days, then find the number of days taken by D to complete (1/5)th of the same work.Solution
Let the total work (LCM of 10, 20 and 30) = 60 units Efficiency of A = 60/10 = 6 units/day Efficiency of B = 60/20 = 3 units/day Efficiency of C = 60/30 = 2 units/day Work done by A and C together in 6 days = 6 × (6 + 2) = 48 units Remaining work = 60 – 48 = 12 units Efficiency of D = (12/3) – 3 = 1 unit/day Number of days taken by D to complete (1/5)th of the same work = (60/5)/1 = 12 days
Find the correct word.
Select the most appropriate meaning of the given idiom.Â
Take exception
Tepid (A) / timid (B) economic growth hasn’t helped, and states have had to resort to higher market borrowings.
The Centre has been short-chan...
Ubiquitous
ENRAVISH - The classical dancer gave such a performance that enravished the audience.Â
Select the most appropriate option to replace the bold word in the given Sentence.
What are a few factors that contributes to water pollution?
Select the most appropriate meaning of the given idiom.
Go the extra mile
The association has welcomed (A) the decision to administer (B) booster dose to senior citizens and community workers and has called for stocking (C) u...
During the pandemic, especially (A) in 2020, the station officer earmarked (B) specific timing for each complainant (C) to address their griefances (D) ...
Any prolonged (A) / impersonating (B) attempt to isolate the country would not only have economic consequences but also complicate the fight against the...