Question
A, B and C can complete a work in 10 days, 20 days and
30 days respectively. A and C started the work together and they both work for 6 days. If the remaining work is completed by B and D in 3 days, then find the number of days taken by D to complete (1/5)th of the same work.Solution
Let the total work (LCM of 10, 20 and 30) = 60 units Efficiency of A = 60/10 = 6 units/day Efficiency of B = 60/20 = 3 units/day Efficiency of C = 60/30 = 2 units/day Work done by A and C together in 6 days = 6 × (6 + 2) = 48 units Remaining work = 60 – 48 = 12 units Efficiency of D = (12/3) – 3 = 1 unit/day Number of days taken by D to complete (1/5)th of the same work = (60/5)/1 = 12 days
More Time and work Questions
- Which letter-cluster will replace the question mark (?) in the following series?
NPQR, OORQ, PNSP, ____, RLUN - Select the number from among the given options that can replace the question mark (?) in the following series.
17, 18, 22, 31, 47, ___ - Which letter and number cluster will replace the question mark (?) to complete the given series?
LT6, KU12, IW24, FZ48, ____ - Which letter-cluster will replace the question mark (?) in the following series?
RGV, UME, ?, AYW, DEF - A series is given with one term missing. Choose the correct alternatives from the given ones that will complete the series.
57, 59, 56, 61, 54, ___