πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A, B and C can complete a work in 10 days, 20 days and

      30 days respectively. A and C started the work together and they both work for 6 days. If the remaining work is completed by B and D in 3 days, then find the number of days taken by D to complete (1/5)th of the same work.
      A 10 days Correct Answer Incorrect Answer
      B 12 days Correct Answer Incorrect Answer
      C 14 days Correct Answer Incorrect Answer
      D 15 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let the total work (LCM of 10, 20 and 30) = 60 units Efficiency of A = 60/10 = 6 units/day Efficiency of B = 60/20 = 3 units/day Efficiency of C = 60/30 = 2 units/day Work done by A and C together in 6 days = 6 Γ— (6 + 2) = 48 units Remaining work = 60 – 48 = 12 units Efficiency of D = (12/3) – 3 = 1 unit/day Number of days taken by D to complete (1/5)thΒ of the same work = (60/5)/1 = 12 days

      Practice Next

      Relevant for Exams:

      ask-question