Question
Aβ and βBβ together can complete a work in 15 days
while βAβ takes 20 days to complete the same work alone. If βCβ is 50% more efficient than βBβ, then find the time taken by βCβ alone to complete the whole work.Solution
Let the total work = 60 units Efficiency of (A + B) = 60/15 = 4 units/day Efficiency of βAβ = 60/15 = 3 unit/day Therefore, efficiency of βBβ = 4 β 3 = 1 units/day Efficiency of βCβ = 1.5 Γ 1 = 1.5 units/day Required time taken = 60/1.5 = 40 days
Which of the following NIT recently will come up with first green tech incubation centre?
Which Indian bank raised βΉ5,000 crore through long-term infrastructure bonds in 2024?
What is the name of the Indian mission sent by ISRO to study the Sun?
Apple iPhone exports account for approximately what percentage of Indiaβs total smartphone exports?
Consider the following statements about the V. Shantaram Lifetime Achievement Award:
1. It is awarded for contributions to feature films.
...
What was the theme of World Consumer Rights Day 2022?
Karpoori Thakur belonged to which state in India?
With reference to Ayushman Bharat Digital Mission, consider the following statements: (2022)
I. Private and public hospitals must adopt it.
<...SEBI has given a nod to launch an IPO toΒ which Small finance bank that is first to have begun operations as an SFB?
Which of the following states is not included in the Green National Highway Corridors Project for which India and the World Bank have signed a loan agre...