Question
A can complete a work in 30 days. B takes 6 days less
than A to complete the same work. In how many days can both of them together complete 90% of the work together?Solution
Time taken by B to complete the work = 30 – 6 = 24 days Let the total work = 120 units Efficiency of A = 120/30 = 4 units/day Efficiency of B = 120/24 = 5 units/day Required time taken = 0.90 x 120/(4+5) = 12 days
If the R2 value for a regression line is 0.60 for 50 observations. What is the adjusted Rsquare value if the number of independent variabl...
In a small open economy with a floating exchange rate, the supply of real money balances is fixed and a rise in government spending ______
Which of the following is/are included while calculating the national income using the income method?
(1) Wages and salaries in cash
...
GDPf = Gross Domestic Product at Factor Cost; GDPm = Gross Domestic Product at Market Price; NNPf = Net National Product at Factor Cost; C = Consumption...
Suppose that a firm has the cost function for a plant as given below
C(w, r, q) = 0.5q(w+r)
where q is output, w is the cost of labour l a...
An analyst has data on wages for 100 individuals. The arithmetic mean of the log of wages is the same as:
Which of the following pairs of goods is/are likely to have a positive cross price elasticity of demand?
(1) Cars and Petrol
(2) Tea ...
The __________________test in econometrics begins by assuming that a defining point exists and can be used to differentiate the variance of the error term.
When the value of d=2, in case of Durbin-Watson Test, what should be done with the null hypothesis?
Suppose your data produces the regression result y = 10 +3x. Scale y by multiplying observations by 0.9 and do not scale x. The new intercept and slope ...