Question
A can complete a work in 30 days. B takes 6 days less
than A to complete the same work. In how many days can both of them together complete 90% of the work together?Solution
Time taken by B to complete the work = 30 – 6 = 24 days Let the total work = 120 units Efficiency of A = 120/30 = 4 units/day Efficiency of B = 120/24 = 5 units/day Required time taken = 0.90 x 120/(4+5) = 12 days
The pH of blood is primarily regulated by:
Which chemical is used to make artificial rain?
What is the product of the reaction?
CH₃COOH + CH₃OH → (H⁺, heat)
A mobile phone charger is
Insulin is secreted by which organ?
Noise is measured in –
The Weight of an object on Earth is 600 N. What will be its weight on moon?
Which of the following is an unsaturated hydrocarbon ?
The sharpness of a television image is termed as its –
NaOH + HC1 -> NaCl + H₂ O in the given chemical reaction