📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store

    • Question

      A can complete a work in 30 days. B takes 6 days less

      than A to complete the same work. In how many days can both of them together complete 90% of the work together?
      A 8 days Correct Answer Incorrect Answer
      B 6 days Correct Answer Incorrect Answer
      C 10 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Time taken by B to complete the work = 30 – 6 = 24 days Let the total work = 120 units Efficiency of A = 120/30 = 4 units/day Efficiency of B = 120/24 = 5 units/day Required time taken = 0.90 x 120/(4+5) = 12 days

      Practice Next
      ask-question