Question
A can complete a work in 30 days. B takes 6 days less
than A to complete the same work. In how many days can both of them together complete 90% of the work together?Solution
Time taken by B to complete the work = 30 – 6 = 24 days Let the total work = 120 units Efficiency of A = 120/30 = 4 units/day Efficiency of B = 120/24 = 5 units/day Required time taken = 0.90 x 120/(4+5) = 12 days
A cone has a base radius of 6 cm and a height of 8 cm. Find its volume and slant height (use π = 3.14).
120Â Â 124Â Â 151Â Â 167Â Â Â 292Â Â Â ?
Factor the polynomial: x³ - 6x² + 11x - 6.
What is the function of the "IF" function in Excel?
The simplified value of (452 x 452 x 452 – 356 x 356 x 356)/(452 x 356 + 452 x 452 + 356 x 356) is:
A bag contains 8 black and 10 white balls. One ball is drawn at random. What is the probability that the ball drawn is white?
In the figure, ABCD is a cyclic quadrilateral with O as center of the circle If ∠BOC = 136°, find ∠OBC.