Question
A can complete a work in 30 days. B takes 6 days less
than A to complete the same work. In how many days can both of them together complete 90% of the work together?Solution
Time taken by B to complete the work = 30 β 6 = 24 days Let the total work = 120 units Efficiency of A = 120/30 = 4 units/day Efficiency of B = 120/24 = 5 units/day Required time taken = 0.90 x 120/(4+5) = 12 days
What is the square root of 5476?
Find the square of 572
Solve the following :-
Determine the value of (0.88)2Β
Find the value of β 474552
Two times a number, added to the square of that number, gives 3. What could be the possible answer for this number?
A horse is tethered to a peg fixed at one corner of a rectangular grass field measuring 45 metres in length and 25 metre...
Find the Square root of β14641
Find the square root of 0.0324.
Find the Square root of β1681