      Question

      ‘A’ alone can complete a work in 10 days. ‘B’

      alone can complete the same work in 15 days. If ‘A’ and ‘B’ work together for 3 days, then the remaining work can be completed by ‘A’ alone in how many days?
      A 3 days Correct Answer Incorrect Answer
      B 4 days Correct Answer Incorrect Answer
      C 5 days Correct Answer Incorrect Answer
      D 7 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let the total amount of work = 30 units {LCM of 10 and 15} Then, efficiency of ‘A’ = 30/10 = 3 units/day Efficiency of ‘B’ = 30/15 = 2 units/day Combined efficiency of ‘A’ and ‘B’ = 3 + 2 = 6 units/day Work completed by ‘A’ and ‘B’ together in 3 days = 5 × 3 = 15 units Remaining work = 30 – 15 = 15 units Time taken by ‘A’ alone to complete the remaining work = 15/3 = 5 days