Question

    A buffalo alone can plough field ‘A’ in 30 days. A

    Bull alone can plough the field ‘A’ in 36 days. Find the number of days taken by 2 bulls and 1 buffalo to together plough field ‘B’ that is 20% larger than field ‘A’?
    A 10.5 days Correct Answer Incorrect Answer
    B 11.5 days Correct Answer Incorrect Answer
    C 13.5 days Correct Answer Incorrect Answer
    D 12.5 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Let the total work done to plough field ‘A’ = 180 units (LCM of 30 and 36) Then, efficiency of a buffalo = (180/30) = 6 units/day Efficiency of a bull = (180/36) = 5 units/day Total work required to plough field ‘B’ = 180 × 1.20 = 216 units Combined efficiency of 2 bulls and 1 buffalo = 5 × 2 + 6 × 1 = 16 units So, number of days required to plough field ‘B’ = 216/16 = 13.5 days

    Practice Next

    Relevant for Exams: