Question

A work can be completed by ‘A’ and ‘B’, alone in 12 days and 14 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if ‘A’, ‘B’ and ‘C’ together can complete the whole work in 3 days.

A 5.6 days
B 3.6 days
C 4.6 days
D 2.6 days