Question
A, B, and C together can do a work alone in 14 days, 35 days, and 70 days respectively. A alone starts the work and work for 3 days and leaves the work, then B alone does the work for 8 days and leaves the work. If remaining work is done by C alone then for how many days has C worked?
More Time and work Questions
- 2 men and 3 boys can do a piece of work in 405 days while 3 men and 2 boys can do the same work in 324 days. In how many days can 5 men and 5 boys do that ...
- Manoj can complete a job in 10 days which Rakesh can do in 15 days. Rakesh can finish a task in 20 days which Suresh can complete in 25 days. In how many d...
- P is 60% more efficient than Q. P takes 30 more days to finish a work as compared to the number of days taken by P and Q together to finish the same work. ...
- Three pipes A, B and C can fill/empty a tank. A can fill it in 12 hours, B in 15 hours, and C can empty a full tank in 20 hours. All three pipes are opened...
- Workers A and B can finish a task in 30 days when working together. They worked for 18 days, and then C completed the rest of the task alone in 12 days. Ho...
- 48 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for 48 ...
- ‘P’ and ‘Q’ can complete a task together in 30 days. If ‘P’ is 60% more efficient than ‘Q’, how many days will ‘Q’ take to finish the work alone?
- Rahul, Rohit, and Raj alone can complete a project in 40, 80, and 120 days respectively. All of them started working together, but after 10 days, Rahul lef...
- Armaan and Bhanu jointly received Rs. 9,000 for completing a task, with Bhanu's share being Rs. 3,000. If Bhanu can complete the work on his own in 48 days...
- ‘A’ can complete 50% of a work in 6 days. ‘B’ takes 4 days more than ‘A’ to complete the work and ‘B’ is 25% more efficient than ‘C’. ‘A’ started the work ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)