Question
P and Q can complete a work in 32 days and 48 days,
respectively. P, Q and R together can complete the work in 16 days. If R get a total wage of Rs. 6240 to complete the work alone, then find the per day wage of R.Solution
Let the total work be LCM of (32, 48 and 16) = 96 units Number of units of work done by P alone in one day = 96/32 = 3 units Number of units of work done by Q alone in one day = 96/48 = 2 units Number of units of work done by P, Q and R together in one day = 96/16 = 6 units Number of units of work done by R alone in one day = 6 – 3 – 2 = 1 unit So, time taken by R alone to complete the work = 96/1 = 96 days So, per day wage of R = 6240/96 = Rs. 65
Which of the following is not in the top five of the world's most recognizable brands?
The recently signed Indo-Pacific Economic Framework (IPEF) focuses on collaboration between which countries?
Name the Goa-based airline that became the first to operate a flight to Lakshadweep.
What is manganese used for ?
India’s foreign exchange reserves are sufficient to cover how many months of projected imports according to an RBI report?
As per Organisation for Economic Co-operation and Development (OECD) data for the year 2020, which country has the highest per capita total spending on ...
Gurpurab is celebrated by which of the following community?Â
As per the RBI report 2023, the projected real GDP growth for FY24 stands at ______Â
'Milk Fever' disease in cows and buffaloes is caused due to
Which British scientist is known for developing the principle of holography in 1947 to improve the resolution of the electron microscope?