P and Q can complete a work in 32 days and 48 days,
respectively. P, Q and R together can complete the work in 16 days. If R get a total wage of Rs. 6240 to complete the work alone, then find the per day wage of R.Solution
Let the total work be LCM of (32, 48 and 16) = 96 units Number of units of work done by P alone in one day = 96/32 = 3 units Number of units of work done by Q alone in one day = 96/48 = 2 units Number of units of work done by P, Q and R together in one day = 96/16 = 6 units Number of units of work done by R alone in one day = 6 – 3 – 2 = 1 unit So, time taken by R alone to complete the work = 96/1 = 96 days So, per day wage of R = 6240/96 = Rs. 65
Given below are four jumbled sentences. Select the option that gives their correct order.
A. The guard escorted him to the front office.
<...Which is the FOURTH sentence of the paragraph?
1. The director of the research organization
P. cactus in food
Q. and nutritional security
R. elaborated on the
S.�...
Given below are six sentences. A and F are the first and the last sentences. The rest of the sentences namely B, C, D and E are jumbled. Select the opt...
Select the most appropriate sequence from the given options to make a meaningful paragraph from jumbled sentences.
A. She was a tall woman and ...
Which of the following is the first sentence of the passage?
Given below are four jumbled sentences. Pick the option that gives their correct order.
A. This invention has helped us to heal wounds caused by ...
Given below are four jumbled sentences. Select the option that gives their correct order
A. However, they ignore the truth that progress and succ...
Which should be the second sentence after rearrangement?
Officials
P: to negotiate a solution
Q: readiness
R: have signaled India’s