Let the total work be LCM of (32, 48 and 16) = 96 units Number of units of work done by P alone in one day = 96/32 = 3 units Number of units of work done by Q alone in one day = 96/48 = 2 units Number of units of work done by P, Q and R together in one day = 96/16 = 6 units Number of units of work done by R alone in one day = 6 – 3 – 2 = 1 unit So, time taken by R alone to complete the work = 96/1 = 96 days So, per day wage of R = 6240/96 = Rs. 65
Recently which states govt inks MoUs worth Rs 18,590 cr with UAE based companies?
INS Shivalik is set to participate in the Rim of the Pacific (RIMPAC) exercise. Where will this exercise be conducted?
Reserve Bank of India aims to enable ____ villages across the country with digital payments through awareness and support from local entrepreneurs and m...
Which of the following international organization has approved loans of $1.75 billion (around Rs 13,834.54 crore) to fund India's PM Ayushman Bharat sch...
Production of eight infrastructure sectors stood at _____in December 2022 against 4.1 percent in the same month of the previous year on a better show by...
Who has been declared as the National Icon of the Election Commission of India?
What does the 'Sangam: Digital Twin' initiative by the Department of Telecommunications (DoT) aim to achieve?
Recently Karnataka Bank has opened Analytical Centre of Excellence ( ACoE) at which place which will help in accelerated incubation of artificial intell...
Recently RBI has imposed a penalty of Rs 27.5 lakh in which public sector bank?
How much fine has been imposed by the Reserve Bank of India on Punjab and Sind Bank for non-compliance with certain directions on 'Loans and Advances St...