Question
A and B individually can complete the work in 30 days and 45 days respectively. If the time taken by C alone to complete the work is 1.5 times the time taken by A and B together to complete the work, find the time taken by C to complete the work while working alone.
More Time and work Questions
- Aaru Swati and Rajni can finish a work in 4 days if they work together. However, Aaru alone will take 9 days to complete the work, and Swati alone will com...
- Ten men begin to do work. But after some days, four of them left the job. As a result, the job that could have been completed in 40 days is completed in 50...
- 'A' and 'B' alone can complete a work in 9 days and 18 days, respectively. Find the time taken by them to complete the work if they work on alternate days ...
- If 6 women can complete a work in 3 days, and 9 girls can complete the same work in 2 days, then find the time taken to complete the same work by 8 women a...
- ‘A’ and ‘B’ can do a piece of work in 10 days and 15 days, respectively. They started working together but ‘A’ left after 3 days. Find the time taken by ‘B...
- ‘Z’ alone can complete a project in 48 days, while ‘Z’ and ‘Y’ together can finish it in 16 days. If ‘Y’ worked alone for ‘x’ days and then ‘Z’ completed t...
- X can finish a task in 20 days, while Y can do it in 25 days. If Z needs 1.2 times the time taken by X and Y together, find the number of days Z will take ...
- A builder recruited 60 workers to do a task in 90 days. It was discovered that only 1/3 of the task was achieved after 60 days. Determine how many addition...
- A can complete a piece of work in 24 days and B can complete it in 36 days. They work together for 8 days, after which A leaves. In how many more days will...
- 'A' alone can do some work in 12 days, 'B' alone can do the same work in 24 days. If they work on alternate days, starting with 'B', then the work will be ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)