Question
A, B and C alone can complete a work in 20, 30 and 25
days respectively. All of them started working together but after 4 days from start A left the job and after 5 more days B also left the job. So for how many days did C work?Solution
Let the total work = 300 units (LCM of 20, 30 and 25) Amount of work done by A alone in one day = 300/20 = 15 units Amount of work done by B alone in one day = 300/30 = 10 units Amount of work done by C alone in one day = 300/25 = 12 units Amount of work done by A, B and C together in 4 days = 4 × (15 + 10 + 12) = 148 units Amount of work done by B and C together in 5 days = 5 × (10 + 12) = 110 units Remaining work = 300 – 148 – 110 = 42 units So, the time taken by C alone to complete 42 units work = 42/12 = 3.5 days So, C worked for 3.5 + 4 + 5 = 12.5 days
If the entry code for Batch A on Thursday (4th May,2017) was “camera affixes to the hands knuckles that takes in”, then which of the fol...
What is the difference between the numbers which is third from the right end and second from the left end in Step V?
Input for Qs. 6 - 10: 28 33 92 35 73 46 84 11
In step II of th...
Which of the following would be the last step of the rearrangement?
How many steps are required to complete the given arrangement?
Step II of an input is: with the blurry photo of herself a
Which of the following is definitely the input?
What will be the 14th step for the following input?
Input: the rule changes will come into effect for
...Which element is between “depths” and “vitae” in step IV?
Who sits second to the right of seventh letter from right in step VI?
Which of following is correct with respect to the position of ‘63’ in step-V?