Question
A, B and C alone can complete a work in 20, 30 and 25
days respectively. All of them started working together but after 4 days from start A left the job and after 5 more days B also left the job. So for how many days did C work?Solution
Let the total work = 300 units (LCM of 20, 30 and 25) Amount of work done by A alone in one day = 300/20 = 15 units Amount of work done by B alone in one day = 300/30 = 10 units Amount of work done by C alone in one day = 300/25 = 12 units Amount of work done by A, B and C together in 4 days = 4 × (15 + 10 + 12) = 148 units Amount of work done by B and C together in 5 days = 5 × (10 + 12) = 110 units Remaining work = 300 – 148 – 110 = 42 units So, the time taken by C alone to complete 42 units work = 42/12 = 3.5 days So, C worked for 3.5 + 4 + 5 = 12.5 days
The relationship between the unemployment rate and the gross national product is depicted by
Which of the following functions has a degree of homogeneity not equal to unity?
Suppose there is a pond with fishes and “n” number of fishermen living around it. Let a i is time spent fishing per day by player i. Thus total time...
A producer received ₹ 6,000 when the price of a commodity was ₹ 60 per unit. The receipts increased to ₹ 8,400 when the price increased by ₹ 10....
What is the currency deposit ratio (cdr)?
With reference to Pradhan Mantri Kaushal Vikas Yojana, consider the following statements:
- It is the flagship scheme of ...
Suppose the wedding dress industry is a perfectly competitive constant cost industry. Suppose also that market demand for wedding dresses is described b...
Approximately what is the Coefficient of Variation of first 50 natural numbers ?
Given the demand function QD=100−2P and the supply function QS=3P−50, where QD is the quantity demanded, QS is the quantity supplied, and P is the p...
Endogeneity in regression arises when: