Question
A, B and C alone can complete a work in 20, 30 and 25
days respectively. All of them started working together but after 4 days from start A left the job and after 5 more days B also left the job. So for how many days did C work?Solution
Let the total work = 300 units (LCM of 20, 30 and 25) Amount of work done by A alone in one day = 300/20 = 15 units Amount of work done by B alone in one day = 300/30 = 10 units Amount of work done by C alone in one day = 300/25 = 12 units Amount of work done by A, B and C together in 4 days = 4 × (15 + 10 + 12) = 148 units Amount of work done by B and C together in 5 days = 5 × (10 + 12) = 110 units Remaining work = 300 – 148 – 110 = 42 units So, the time taken by C alone to complete 42 units work = 42/12 = 3.5 days So, C worked for 3.5 + 4 + 5 = 12.5 days
A funding of $122 million to the top three Indian medical research institutions has recently been announced by which country?
Faster Adoption and Manufacturing of (Hybrid &) Electric Vehicles in India (FAME India) is being implemented by ministry of ________?
What is the objective of the MoU between IFSCA and CPI?
NABARD is working towards helping the farmers tackling the adverse impact climate change.For this purpose it has collaborated with __________ and Bill a...
Who holds the record for the most swims across the English Channel?
To create the school infrastructure in the state a campaign has been launched by the government named as ‘Mana Ooru Mana Badi”. Name the state?
The Ahmedabad Police Command and Control Centre uses which technology for enhanced surveillance?
India has won many gold medals in Archery World Cup Stage 1 in Turkey, Istanbul?
India has lost (X) hectares of tree cover since 2000, marking a 6% decrease in tree cover during this period, based on Global Forest Watch data ?
Which of the following is NOT a focus area of the AVGC-XR policy?