Question
‘A’ alone can complete a work in 60 days while
‘A’ and ‘B’ together can complete the same work in 42 days. How much percentage of the work, ‘B’ alone can complete in 63 days?Solution
Let the total work = L.C.M of 60 and 42 = 420 units Then, efficiency of ‘A’ alone = 420 ÷ 60 = 7 units/day Combined efficiency of ‘A’ and ‘B’ = 420 ÷ 42 = 10 units/day So, efficiency of ‘B’ = 10 – 7 = 3 units/day So, work done by ‘B’ alone in 63 days = 3× 63 = 189 units So, percentage of work completed by ‘B’ = (189 ÷ 420) × 100 = 45%
Statement:
P < M ≤ Y = X; U > A =C; P < C = O > E
Conclusions:
I). Â Y > C
II). Â X < E
...if at point O the person starts walking to this west and walks for 9km reaches point A, then what will be the distance between point J and A?<...
If U walks 18m towards the west and then takes a left turn of 24m then, what is the shortest distance between Q and U finally?
Four of the following five are related to each other in some manner to form a group. Which of the following doesn't belong to that group?Â
Shipra set out to her grandmother's home. She leaves her house and first took a left turn. Then she took a right turn and a right and a left and a right...
Point C is in which direction with respect of Point B?
Kirti started walking towards South. After walking 100 meters she turned to her Left and walked 60 meters and took a left turn and walked 50 meter. Agai...
P is 30 meter to the East of Q. R is 26 meter to the north of Q and 10 meter to the west of S. T is 40 meter to the South of S. T is 20 meter to the Wes...
What is the direction of point X with respect of point V?
In a certain code language, "CANDLE" is coded as 42155136, and "BRIGHT" is coded as 319108921. How will "SHADOW" be coded?