‘A’ alone can complete a work in 50 days while
‘A’ and ‘B’ together can complete the same work in 30 days. How much percentage of the work, ‘B’ alone can complete in 63 days?Solution
Let the total work = L.C.M of 50 and 30 = 150 units Then, efficiency of ‘A’ alone = 150 ÷ 50 = 3 units/day Combined efficiency of ‘A’ and ‘B’ = 150 ÷ 30 = 5 units/day So, efficiency of ‘B’ = 5 – 3 = 2 units/day So, work done by ‘B’ alone in 63 days = 2 × 63 = 126 units So, percentage of work completed by ‘B’ = (126 ÷ 150) × 100 = 84%
Which of the following is known as the brain of the Computer System?
NAHB related to?
During which decade did India experience a negative growth rate in its population for the first time?
The Vindhyachal Thermal Power Station is located in which state?
Which is the highest peak in the Western Ghats?
Identify the element with the highest atomic mass from the list below:
World Rabies Day is observed every year on ____________
The famous Blue Revolution is related to which_____?
The National Game of Bhutan is
Which of these are names of Indian satellites?