Question
‘A’ alone can complete a work in 45 days while ‘A’ and ‘B’ together can complete the same work in 35 days. How much percentage of the work, ‘B’ alone can complete in 63 days?
More Time and work Questions
- A man can complete a task in 20 days, a woman can finish it in 30 days, and a boy can do the same task in 60 days. To complete the task in just 3 days, how...
- Akhil and Nikhil together can complete a work in 15 days while Nikhil alone takes 20 days to complete 50% of the work. If the efficiency of Sachin is 20% m...
- A, B and C can complete a work in 2 days. If A alone can complete the same work in 6 days and B in 4 days, how long will it take for C to finish the work a...
- Eight men and five boys together earn ₹3,240 in 6 days. Meanwhile, three men and two boys working together take 12 days to earn ₹2,484. How many days will ...
- Karan and Kavya, alone can complete a work in 16 days and 24 days, respectively. They started the work together and left after 6 days such that the remaini...
- (x + 3) workers complete 50% of work in 4 days at 5 hours/day. (x + 1) workers finish the rest in 5 days at 6 hours/day. Find x.
- ‘P’ can complete a project in 12 days. ‘Q’ is 40% less efficient than ‘P’. Working together, ‘P’, ‘Q’ and ‘R’ can finish the job in 5 days. In how many day...
- Armaan can complete a task in 36 days, Bittu in 45 days, and Chirag in 60 days. If Bittu and Chirag together work on the task for 10 days, how many additio...
- Ganga, Yamuna &Saraswati can complete a piece of work in 30, 40 & 60 days respectively. All 3 of them started working together and after 4 days, Ga...
- Anil and Ashish receive Rs.1200 for work of 8 days. If Anil is 5 times efficient than Ashish, then find the daily wage received by Ashish.