Let the total work = L.C.M of 45 and 35 = 315 units Then, efficiency of ‘A’ alone = 315 ÷ 45 = 7 units/day Combined efficiency of ‘A’ and ‘B’ = 315 ÷ 35 = 9 units/day So, efficiency of ‘B’ = 9 – 7 = 2 units/day So, work done by ‘B’ alone in 63 days = 2 × 63 = 126 units So, percentage of work completed by ‘B’ = (126 ÷ 315) × 100 = 40%