Question
Working alone, B can complete the work in 16 days. C is twice as efficient as B and A takes 4 days more than it takes C to complete the work. Working together, in how much time would they be able to complete 13 such works?
More ESIC Part B Questions
- According to the reverse dictionary order, which of the following words will come at the first position? 1. Table 2. Talent 3. Tackle 4. Talon 5. Tang...
- Who is the author of the work, The Evolution of Provincial Finance in British India : A Study in the Provincial Decentralization of imperial Financer?
- Average marks scored by Vineet in five subjects are 80. The average marks scored by him (excluding his highest and lowest marks) are 65 and lowest marks sc...
- In British India “C-R Formula” was associated with?
- In a given years, A sold 700 caps while B sold 65% more number of caps than A and C sold 20% less number of caps than B. Find the ratio between the number ...
- How many participants from India won the gold medal in the 14th International Olympiad on Astronomy and Astrophysics (IOAA) 2021?
- As per the Economic Survey 2022-23, which of the following statement is/are incorrect? I. Unemployment rates fall from 5.8 per cent in 2018-1...
- Select the number from among the given options that can replace the question mark (?) in the following series: 26, 78, 36, 108, 66, 198, ?
- What kind of penalty is there on an “illegal strike”?
- In a park, the ratio of oak to pine trees is 7:4. If 21 oak trees and 12 pine trees are planted, the ratio of pine trees to oak trees becomes 3:5. Find the...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)