X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
More Time and work Questions
- A, B and C can do a piece of work in 5, 8 and 10 days respectively. They start working together but C leaves after working 1 days and B, 2 days before the ...
- Akhil and Nikhil together can complete a work in 6 days while Nikhil alone takes 18 days to complete 60% of the work. If the efficiency of Sachin is 25% mo...
- A can complete a work in 18 days , B in 24 days , and C in 36 days . A starts the work alone and works for 4 days . Then B joins him, and after 3 more...
- B is 20% more efficient than A. If B was 60% more efficient than A, then, B could complete the work in 18 days lesser than days taken by A. What fraction o...
- 35% of the work done by Sunil in 8 days is equal to 70% of the work done by Raj in 3 days. If Sunil alone can do the work in 24 days, find the number of da...
- When working alone, Ansh takes 12 more days than time taken by Ansh and Balu together to finish certain work. If Ansh is 50% more efficient than Balu, then...
- 'Meera', 'Kiran', and 'Suman' together can complete a work in 30 days. 'Meera' and 'Kiran' together can complete the same work in 90 days. 'Suman' alone ca...
- Alok and Vinay can complete some work alone in 12 days and 20 days respectively. Both of them started the work together but Vinay left the work 4 days befo...
- 24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the same work in 60 days. Which...
- A2 type ‘P’ pipes can fill a tank in 350 hours, while B2 type ‘Q’ pipes can fill the same tank in 504 hours. (10A × 6B) type ‘P’ pipes can fill the same ta...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt