A and B together can complete a piece of
work in 45 days while B and C together can complete the same work in 55 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. valueSolution
Time taken by A, B and C together to complete the whole work = 26.4/0.80 = 33 days
Let total amount of work = 495 (LCM of 45, 55 and 33)
Efficiency of (A + B) = 495/45 = 11 units per day
Efficiency of (B + C) = 495/55 = 9 units per day
Efficiency of (A + B + C) = 495/33 = 15 units per day
Efficiency of A = 15 – 9 = 6 units per day
Efficiency of C = 15 – 11 = 4 units per day
Desired time = 495/10 = 49.5 days = 50 days
More Time and work Questions
Arabian Jasmine species is
National Centre for Organic and Natural farming is located at ____
Bacteria responsible for nitrogen fixation in soybean is
Which among the following is a goal of Integrated Pest Management (IPM) ?
The genetic cause(s) of heterosis include:
Which monsoon is responsible for rainfall in tamil nadu
Who is known as the “Father of Indian Soil Science”?
Training Rural Youth for Self Employment (TRYSEM) was launched by the Government of India in:
The national flower of India, which also has religious and ornamental significance, is:
The physiological disorder “ Hen and Chicken” is likely to affect which crop?