Question

Abhishek, Rohit and Pankaj working together completed a job in 20 days. The ratio of their efficiencies is 3 : 4 : 5. How many days will be required by the fastest worker alone to complete the whole work?

A 17 days
B 48 days
C 37 days
D 73 days