      Abhishek, Rohit and Pankaj working together completed a

      job in 20 days. The ratio of their efficiencies is 3 : 4 : 5. How many days will be required by the fastest worker alone to complete the whole work?
      A 17 days Correct Answer Incorrect Answer
      B 48 days Correct Answer Incorrect Answer
      C 37 days Correct Answer Incorrect Answer
      D 73 days Correct Answer Incorrect Answer

      Solution

      Ratio of efficiencies = 3 : 4 : 5 & they together completed a job in 20 days. So let total work = (3+4+5)`xx` 20 = 240 units So fastest person will do the job in = 240/5 = 48 days