Question
Abhishek, Rohit and Pankaj working together completed a
job in 20 days. The ratio of their efficiencies is 3 : 4 : 5. How many days will be required by the fastest worker alone to complete the whole work?Solution
Ratio of efficiencies = 3 : 4 : 5 & they together completed a job in 20 days. So let total work = (3+4+5)`xx` 20 = 240 units So fastest person will do the job in = 240/5 = 48 days
Consider the following statements:
1.The Prime Minister of India must be a member of the Lok Sabha or the Rajya Sabha.
2.The President of ...
In which of the following cases the Supreme Court, while laying out the ‘basic structure’ of the Constitution held that the democratic character of ...
Which of the following is an alarming effect of thermal pollution in water bodies?
By what name is the Parliament of Israel known?
Which writer has been honored with the '33rd Vyas Samman' in the year 2023?
Which of the following options are all transition metals?
According to a written reply to the Lok Sabha by Government of India, as on 20 July 2022, approximately _________ unorganised sector workers are registe...
National Voters Day is celebrated on 25 January to encourage the youth to participate in the vote in the electoral process. What is the theme for the ye...
Who among the following called the Revolt of 1857 a ‘National Revolt’?
______ is reducing the degree or intensity of, or eliminating, pollution.