Question
Gagan can do a piece of work in 14 days. Magan is 40% more efficient than Gagan. How many days will Magan and Gagan together complete the work?
More Time and work Questions
- 12 man can make a wall in 5 days. How many men required to complete the same work in 6 days ?
- Anupam can do a piece of work in 36 days and Rajveer can do it in 15 days. Diksha can do the same work in (17/18) times the number of days required by both...
- A2 type ‘P’ pipes can fill a tank in 350 hours, while B2 type ‘Q’ pipes can fill the same tank in 504 hours. (10A × 6B) type ‘P’ pipes can fill the same ta...
- If 24 persons can finish 50% of work in 12 days in how many days 48 person can finish the complete work?
- A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone in 2x...
- A does 1/2 work and B does 3/4 work in the same time. Difference between number of days taken by A and B to work alone to complete the work individually is...
- ‘A’ and ‘B’ can do a piece of work in 10 days and 15 days, respectively. They started working together but ‘A’ left after 3 days. Find the time taken by ‘B...
- It takes a team of either 20 boys or 35 girls, 27 days to achieve a sales target. How many days will it take for a team consisting of 21 boys and 42 girls ...
- A can finish a task in 32 days, while B can complete the same task 8 days sooner than A. If they together earn a total of Rs. 1050 for the job, how much do...
- X men can complete the piece of work in 36 days and (X + 35) men can complete the same work in 14 days less than that of days taken by X men. Find the valu...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)