Question
Anuj, Bittu, and Chintu can individually complete a
certain task in 84 days, 105 days, and 60 days, respectively. They all begin working together, but Bittu leaves after working for 12 days. Determine the total number of days required to complete the entire task.Solution
ATQ, Let total work = 420 days (LCM of 84, 105 and 60) Amount of work completed by Anuj in one day = 420/84 = 5 units Amount of work completed by Bittu in one day = 420/105 = 4 units Amount of work completed by Chintu in one day = 420/60 = 7 units Amount of work completed by Anuj, Bittu and Chintu together in 12 days = 12 × (5 + 4 + 7) = 192 units Amount of time taken by Anuj and Chintu together to complete the remaining work = (420 – 192)/12 = 19 days Desired time = 12 + 19 = 31 days
In this question, there are two statements showing the relationship between the letters and the three conclusions related to them are i, ii and iii. Ass...
Select the option that is related to the third term in the same way as the second term is related to the first term.
MJKH : SPQN :: FCDA : ?
Given in the table are the number codes for the given letters. Select the combination of numbers so that the letters arranged accordingly will form a me...
What should come in place of ? in the given series?
73 75 77 79 81 ?
What should come in place of '?' in the given series?
11 32 74 158 326 ?
Select the correct mirror image of the given figure when the mirror is placed to the right side of the f igure .
Select the option that is related to the third letter-cluster in the same way as the second letter-
cluster is related to the first letter-cluste...
In a certain code language, 'LAMP' is coded as 'IWJL'. What is the code for 'LOGS' in that code language?
What should come in place of ? in the given series based on the English alphabetical order?
ACE, FHJ, KMO, PRT , ?
If '÷' is replaced with '+', '×' is replaced with '–', '+' is replaced with '×' and '–' is replaced with, '÷' then what will be the value of the...