Question
I: A sum of money is to be divided into two parts. One
part is invested at 10% p.a. simple interest for 3 years, and the other part at 8% p.a. simple interest for 3 years. The total simple interest earned from both parts together in 3 years is βΉ10,800. II: If the entire sum had been invested at 10% p.a. simple interest for 3 years, the total simple interest would have been βΉ12,000. What was the amount invested at 8% p.a.?Solution
ATQ, Let total principal = P. From Condition II: If full P at 10% for 3 years: Interest = P Γ 10 Γ 3 / 100 = 30P / 100 = 3P/10 This is given as βΉ12,000: 3P/10 = 12,000 β 3P = 1,20,000 β P = 40,000 Let amount invested at 10% be x. Then amount at 8% is P β x = 40,000 β x. From Condition I: Interest from 10% part (3 years) = x Γ 10 Γ 3 / 100 = 3x/10 Interest from 8% part (3 years) = (40,000 β x) Γ 8 Γ 3 / 100 = (40,000 β x) Γ 24 / 100 = 24(40,000 β x)/100 = (24 Γ 40,000)/100 β 24x/100 = 9,600 β 6x/25 Total interest = 10,800: 3x/10 + 9,600 β 6x/25 = 10,800 Take LCM of 10 and 25 β 50: (15x/50) + 9,600 β (12x/50) = 10,800 (3x/50) + 9,600 = 10,800 3x/50 = 1,200 3x = 60,000 x = 20,000 So amount at 10% = βΉ20,000 Amount at 8% = 40,000 β 20,000 = βΉ20,000 Required: amount invested at 8% p.a. = βΉ20,000.
Atul, Qureshi, and Chintu can individually complete a certain task in 27 days, 30 days, and 36 days, respectively. They all begin working on the task to...
'B' and 'N' can collectively finish a task in 88 days, and 'N' and 'S' together can complete the same work in 66 days. If 'B' and 'S' work together, the...
"Arnav, Bhanu, and Chinu can finish a task in 18 days, 24 days, and 30 days, respectively. They all begin working together, but B...
X men can complete the piece of work in 45 days and (X + 46) men can complete the same work in 23 days less than that of days taken by X men. Find the v...
A and B can each finish a task in 32 days and 36 days respectively. They begin the task together, but after 12 days, A leaves. How long will it take for...
βAβ and βBβ alone can do a certain work in 30 days and 40 days, respectively. Both started the work together but after βxβ days βAβ left...
X can work as fast as Y and Z together. X and Y together can finish the same task 3 times as fast as Z. If all three working together can finish the tas...
- βPβ takes 25 days to complete a piece of work. βQβ is 25% more efficient than βPβ. Find the time taken by them to complete 90% of the work toge...
5 men and 1 boy together can complete a work in 25 days. 3 men and 5 boys can together complete half of the same work in 10 days. Find the time taken by...
Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it ...