Question

The following questions each present two quantities, Quantity I and Quantity
II. Compare the values of the two quantities and determine their relationship. X works at twice the efficiency of Y, and Z works at three times the efficiency of
X. All three working together can finish a job in 12 days. Quantity I: X works alone for the first 14 days and then leaves. After that, Y and Z continue the remaining work on alternate days, with Y taking the first turn. How many total days will it take to finish the entire work? Quantity II: If each of them works alone to complete the entire work, what is the average number of days taken by X, Y, and Z?

A Quantity > Quantity II
B Quantity < Quantity II
C Quantity I = Quantity II or No relation can be established
D Quantity I ≥ Quantity II
E Quantity I ≤ Quantity II
Practice Next

More Quantity Inequality Questions

Hey! Ask a query