Question
The following questions each present two quantities,
Quantity I and Quantity II. Compare the values of the two quantities and determine their relationship. X works at twice the efficiency of Y, and Z works at three times the efficiency of X. All three working together can finish a job in 12 days. Quantity I: X works alone for the first 14 days and then leaves. After that, Y and Z continue the remaining work on alternate days, with Y taking the first turn. How many total days will it take to finish the entire work? Quantity II: If each of them works alone to complete the entire work, what is the average number of days taken by X, Y, and Z?Solution
ATQ, Efficiency of X = 2x Efficiency of Y = x Efficiency of Z = 6x Total work = 9x×12 = 108x Quantity I: In 14 days X has done the work = (14×2) = 28x Remaining work = 108-28 = 80x In 2 days Y and Z will do = 7x units In 22 days then will do =77x units On the next day, Y will do = x unit of work Remaining work = 2x units Z will do the 2x unit work in = 2/6 = 1/3 days Total days taken to complete the work = 14+23 (1/3) days = 37 (1/3) days Quantity II: Time taken by Z alone to complete the whole work = 108x/6x = 18 days Time taken by X alone to complete the whole work = 108x/2x = 54 days Time taken by Y alone to complete the whole work = 108x/x = 108 days Required average = 18+54+108/3 = 60 days
How can you add a transition effect between slides in PowerPoint?
Which of the following file extension denotes Microsoft Power Point Presentation
Which of the following keyboard shortcuts is used to view the properties of a selected object?
Which of the following options in MS Word 365 means the page is oriented vertically?
What is the purpose of the CONCATENATE function in Excel?
Which of the following uses a combination of any two or more topologies
What is the purpose of the "Slide Master" in PowerPoint?
Which one is generally used in banks to process the Cheques?
First row in MS Excel is written as?
What is the short cut key to centre the paragraph?