Question
Quantity I:Â Boat 'P' travels
540 m downstream in 45 seconds, while boat 'Q' travels 240 m upstream in 48 seconds. If the ratio of the speed of boat P in still water to the speed of boat Q in still water is 19:15, find the time it takes for boat 'P' to cover 224 m upstream. Quantity II:Â In a mixture of juice and water, the amount of juice exceeds the amount of water by 6 liters. The ratio of the cost of pure juice to the cost of the mixture is 5:3. If 5 liters of the mixture is replaced with the same quantity of juice, what will be the new cost of the mixture? In the question, two quantities I and II are given. You have to solve both the quantities to establish the correct relation between Quantity-I and Quantity-II and choose the correct option.Solution
ATQ, Quantity I: Let the speeds of boats P and Q in still water are ‘19x’ m/s and ‘15x’ m/s respectively. Also let the speed of the stream is ‘y’ m/s. So, 19x+y= 540/45 19x + y = 12 ---------- (1) And 15x-y= 240/48 15x – y = 5 ---------- (2) From equations (1) and (2): x = 0.5, y = 2.5 Since, the upstream speed of boat P = 19 × 0.5 – 2.5 = 7 m/s So, the time, in which boat P can cover 224 m upstream = 224/7 = 32 seconds Quantity II: Let the initial quantity of water = ‘x’ L So, the initial quantity of juice = (x + 6) L Let the cost of pure juice is Rs.’5y’ per L and the initial cost of the mixture is Rs.‘3y’ per L. So, ((x+6)×5y)/(2x+6)=3y 5x + 30 = 6x + 18 x = 12 The initial quantity of water = 12 L The initial quantity of water = 12 L The initial quantity of juice = 12 + 6 = 18 L After replacing 5 L quantity of the mixture with the same quantity of juice: The new quantity of juice = 18 – 3 + 5 = 20 L The new quantity of water = 12 – 2 = 10 L Since, we don’t know the cost of the pure juice. So, the cost of new mixture can’t be determined. Hence, relation can’t be established
- Amit and Ankit can complete a job in 60 days. Working together with Sumit, they can finish it in 40 days. How many days would Sumit alone take to complete ...
A civil contractor planned to build an over bridge of 3 km distance in 600 days. For this purpose, he employed 90 workers. After 200 days of work, it wa...
Three workers A, B and C can complete a job in 12, 15 and 20 days respectively, working alone. All three start working together. After some time, C leav...
Gagan can do a piece of work in 14 days. Magan is 40% more efficient than Gagan. How many days will Magan and Gagan together complete the work?
Vikram alone can finish some work in 20 days. Vikram and Varun completed the work together and earned Rs. 8,000 as wage. If Varun's wage share is Rs. 3,...
Four boys and nine girls can complete a task in 24 days. Three boys and five girls can finish the same task in 36 days. How many ...
- Alok finishes 60% of a project in 30 days, while Neha finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by...
- A task can be done by ‘p’ men in 32 days. If the team had 8 more men, the work would finish in 24 days. Find the value of ‘p’.
P alone can finish a piece of work ‘M’ in 12 days while Q takes 8 days to finish it alone. P, Q and R working together can finish the work ‘N’ w...
Ashish and Anil can do a piece of work in 20 days and 25 days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete th...