Question
βXβ and βYβ are capable of finishing a work in 9
days and 12 days respectively. They worked together for 3 days. Find the number of days βYβ alone would take to complete the leftover work.Solution
ATQ,
Let the total work be 36 units (LCM of 9 and 12)
Efficiency of βXβ = 36 Γ· 9 = 4 units/day
Efficiency of βYβ = 36 Γ· 12 = 3 units/day
Work done by βXβ and βYβ together in 3 days = 3 Γ (4 + 3) = 21 units
Remaining work = 36 β 21 = 15 units
Time taken by βYβ to finish the remaining work = 15 Γ· 3 = 5 days
Who has been elected for the third term as the President of China?
Which Union Ministry is responsible for implementing the Pradhan Mantri Awas Yojana (Urban)?
Identify the correct statements regarding the employment growth rate in FY24:
1. Employment growth in India increased by 6% in 2023- 24.
2...
Which of the following companies is not in the G7 Group?
What is the name of the first submarine base commissioned by Bangladesh?
Which of the following statements is INCORRECT regarding Indian Constitution articles?Β Β
__________ has been named the recipient of the ICC Spirit of Cricket Award.
What was the value of the ADB loan approved for the Gujarat Skills Development Programme?
Which chemical's countervailing duty was extended by India for five more years?
The famous Sun Temple at Konark was built by ________.