Question
Aman, Bhanu, and Chinu can
complete a piece of work individually in 20 days, 30 days, and 60 days, respectively. How many days will Aman take to finish the work if Bhanu and Chinu assist him every third day?Solution
ATQ,
Work Rates: Aman completes 1/20 of the work per day. Bhanu completes 1/30 of the work per day. Chinu completes 1/60 of the work per day.
Work Schedule:
Total Time: In 3 days, 1/5 of the work is completed. Total work = 1 unit. Cycles needed = 1/(1/5) = 5. Total time = 5Γ3 = 15 days.
Statement: The president of ixambee urged all the employees to refrain from using mobile phones frequently during working hours in order to boost produ...
A statement is given followed by two conclusions numbered I & II. Assuming the statement to be true, even if they seem to be at variance with commonly ...
Authorities of the Government School for Visually Impaired seeking the help of anganwadi teachers to address the decreasing strength of students.
In each question a statement is given, followed by two assumptions, numbered I and II. An assumption is supposed or taken for granted. You have to con...
Statement: The alumni of the institute returned to rescue crumbling building of 112-year-old alma mater.
I. The Building of the institute was b...
The following are the criteria for selecting a website designer for the ABC Media company.
The candidates must:
(a) Have Diploma or degree...
In the question below is given a statement followed by two assumptions numbered I and II. You have to consider the statement and the following assumpt...
Statement: Commuters will have the benefit of parking spaces at a majority of the stations on the Green Line as six out of the 11 yet-t...
Statement: Of the 478 storm water drains identified for clean-up before monsoon in the city, only 167 have been taken up, and work on these is still u...
Statement : "The education board has decided to reduce the syllabus for this academic year."
Assumptions :
I. Reducing the syllabus will...