Question
Aman, Bhanu, and Chinu can
complete a piece of work individually in 20 days, 30 days, and 60 days, respectively. How many days will Aman take to finish the work if Bhanu and Chinu assist him every third day?Solution
ATQ,
Work Rates: Aman completes 1/20 of the work per day. Bhanu completes 1/30 of the work per day. Chinu completes 1/60 of the work per day.
Work Schedule:
Total Time: In 3 days, 1/5 of the work is completed. Total work = 1 unit. Cycles needed = 1/(1/5) = 5. Total time = 5Γ3 = 15 days.
What is the average of first 32 multiples of 3.2?
- Let βpβ denote the number of primes from 1 to 30, and βqβ be the number of prime numbers in the range 31 to 50. What is the product p Γ q?
Find the smallest integer greater than 100 which leaves remainder 4 when divided by each of 5, 6 and 7.
When the digits of a two-digit number are interchanged, the new number becomes 2 more than 200% of the original number. If the sum of the digits is 7, f...
Find the median of 2, 8, 6, 6, 7, 9, 5, 12 and 13.
If the first term of a geometric progression (GP) is 12 and the common ratio is 4, then find the sum of its 4 terms.
Find the unit digit in (257)45 Γ (248)73.
Divide 45 into 4 parts such that if the first is increased by 2, the second is decrease by 2, the third is multiplied by 2 and the fourth divided by 2, ...
Find the range of the given data:
110, 135, 120, 95, 105, 115, 125, 140
Find the third proportion of 38 and 19.