Question
Aman, Bhanu, and Chinu can
complete a piece of work individually in 20 days, 30 days, and 60 days, respectively. How many days will Aman take to finish the work if Bhanu and Chinu assist him every third day?Solution
ATQ,
Work Rates: Aman completes 1/20 of the work per day. Bhanu completes 1/30 of the work per day. Chinu completes 1/60 of the work per day.
Work Schedule:
Total Time: In 3 days, 1/5 of the work is completed. Total work = 1 unit. Cycles needed = 1/(1/5) = 5. Total time = 5×3 = 15 days.
The "Grand Canyon," one of the largest gorges in the world, is formed by which river?
Consider the following statements:
1. The Galwan Valley is located between Ladakh in the west and Aksai Chin in the east.
2. The Ladakh Pl...
In which atmospheric layer is there no decrease in temperature with an increase in altitude?
The Panama Canal connects which two oceans?
Tungabhadra and Bhima rivers are tributaries of which river?
Which of the following statements about rainfall in India is/are correct?
1. Most of the rainfall in India is due to the South-West monsoon
...Which region of Earth's atmosphere is the coldest?
Which of the following are the impacts of ‘La Nina’?
1. Increased temperatures in the Indian Ocean
2. Droughts in Australia
3. ...
Mount Damavand is found in which mountain range?
A cyclone is known by different names in different parts of the world. It is called a ‘________________’ in Japan and Philippines.