Question
To construct a house, 18 workers laboring 5 hours daily
complete the job in 22 days. If the workforce increases to 24 workers, each working 7.5 hours per day, how many days will it take to finish the same house?Solution
Let the efficiency of a man = 'x' units/hour So, total work taken to build a house = 18 X x X 5 X 22 = '1980x' units So, number of days taken by 24 men working 7.5 hours a day to build the house = 1980x ÷ (24 X x X 7.5) = 1980x ÷ 180x = 11
‘A’ and ‘B’ can do a piece of work in 25 days and 30 days, respectively. If they started the work together and worked on it for 5 days, then fin...
Out of 10 men, 3 are wearing red caps, 4 are wearing green caps, and the remaining men are wearing orange caps. They are to be seated in a linear row. I...
In what ratio rice at 47 Rs/kg should be mixed with the rice at 28 Rs/kg so that selling mixture at Rs 45 per kg gives the profit of 25% if the quantity...
33.98 X 17.99 - (7.99 X 8.99) ÷ 1.99 - 27.99 X 4.01 = ? X 3.99
If '176x95' is a six-digit number that is divisible by 3, then find the maximum value of '5x'.
In a Mixture, the ratio of Milk and Water is 7: 5. If 12 litre mixture drawn off and replace by 8 litre water then the ratio of Milk and Water become 1...
A shopkeeper offers successive discounts of 20% and 10% on a product. If the marked price of the product is ₹1000, what is the selling price?
You are provided with three sequences below. Determine the values of P, Q, and R, and then identify the relationship among them.<...
The three digits of a three-digit number are in the ratio 3:2:5. If 111 is added to this number, what is the sum of the digits of the resulting number?
In what ratio rice at 52 Rs/kg should be mixed with the rice at 36 Rs/kg so that selling mixture at Rs 50 per kg gives the profit of 25% if the quantity...